Project Management

Please login or join to subscribe to this thread

What type of schedule should a Scrum Master maintain on an agile project?

linkedin twitter facebook   Agile   Product Management  
avatar
Anonymous
A Scrum Master has been asked to maintain a product schedule. What type of information should be in this schedule? Should this be a prediction of what is to be achieved in each sprint or an overall Project Management schedule to include the activities to operationalize the product? 
Sort By:
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
It could be a high-level one with just one task or activity representing each sprint and an estimated number of sprints to complete a release.

Anything more than that is 100% fiction if the team is truly taking an adaptive approach as there is unlikely to be much clarity about work items beyond the current and at most the next sprint.

Kiron
avatar
Fabian Crosa
Community Champion
PMO Leader | Speaker & Mentor | Content Leader – PMOGA Latin America Hub| Catholic University of Uruguay Montevideo, Montevideo, Uruguay
un cronograma de producto en Scrum debe ser una herramienta dinámica que combine la planificación detallada de cada sprint con una visión general de las actividades necesarias para el éxito del proyecto. Esto permite al equipo adaptarse a los cambios y asegurar que se cumplan los objetivos del proyecto de manera efectiva.
avatar
Srinivas R Lead (SDET / Quality Engineering - Full stack)| Dayforce Inc (Fomerly Ceridian HCM)
Your schedule should include a daily standup's (One or multiple project), Track the workload on every resources, Planned and committed user stories are on schedule from development and testing, Improve the SDLC process if any loopholes, Implement the feedbacks obtained from retro, Track the burndown and project velocity apart from that need to maintain a report on the planned story points vs delivered on each sprints
avatar
Abolfazl Yousefi Darestani Manager, Quality and Continuous Improvement| Hörmann-TNR Industrial Doors Newmarket, Ontario, Canada
I would say a high-level one. I vote for Kiron's comment.
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Is not Product Schedule. It is Product Roadmap. Product Manager is accountable for that.
avatar
Jim Morgan Durham, NC, United States
I will offer the apparently radical position that the Scrum Master should refuse. The SM works with the Product Owner to ensure a Product Backlog is available and prioritized in rank order. That's the end of the SM's responsibility in that area. Once a velocity is established, anyone can look at the backlog, do the math, and figure out when a story they are interested in might be available. (For example, if the velocity is 6 stories per sprint, and the item is #24 on the list, the earliest possible delivery under current priorities is 4 sprints from now.)
...
1 reply by Kiron Bondale
Dec 04, 2024 3:59 PM
Kiron Bondale
...
This is one of the reasons why I favor Disciplined Agile and other agnostic toolkits over rigid frameworks. DA from the get-go has recognized that different stakeholders might want to see information presented in different ways to them, including schedule data.

Here's a page from the DA micro-site providing this info: https://www.pmi.org/disciplined-agile/agile/agilegantt

Kiron
avatar
Ronak Shah QA Automation Engineer| PMI
testing only
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Dec 04, 2024 10:02 AM
Replying to Jim Morgan
...
I will offer the apparently radical position that the Scrum Master should refuse. The SM works with the Product Owner to ensure a Product Backlog is available and prioritized in rank order. That's the end of the SM's responsibility in that area. Once a velocity is established, anyone can look at the backlog, do the math, and figure out when a story they are interested in might be available. (For example, if the velocity is 6 stories per sprint, and the item is #24 on the list, the earliest possible delivery under current priorities is 4 sprints from now.)
This is one of the reasons why I favor Disciplined Agile and other agnostic toolkits over rigid frameworks. DA from the get-go has recognized that different stakeholders might want to see information presented in different ways to them, including schedule data.

Here's a page from the DA micro-site providing this info: https://www.pmi.org/disciplined-agile/agile/agilegantt

Kiron
avatar
FAIZA KHALIL MIS,Policy & Project Coordinator| SAMBA BANK Karachi, Sd, Pakistan

In an Agile project, a Scrum Master maintains a release or sprint schedule, focusing on short, iterative cycles rather than a fixed long-term plan.



This includes:



Sprint calendar (planning, review, retrospective dates)



Daily Scrum schedule



Release roadmap for overall product goals



The emphasis is on flexibility and continuous adjustment, not rigid deadlines.

Please login or join to reply

Content ID:
ADVERTISEMENTS

"I choose a block of marble and chop off whatever I don't need."

- Rodin

ADVERTISEMENT

Sponsors