Which of the following does NOT generate changes to the Project documents?

linkedin twitter facebook   Scheduling  
avatar
Yahya Mohamed Mohamed Ibrahim Planning Engineer| AAW
A) Estimate Activity Resources
B) Estimate Activity Durations
C) Sequence Activities
D) Define Activities
Sort By:
< 1 2 >
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
In the real world, all of these could result in updates to existing documents such as an Assuptions Log or a Risk Register.

Kiron
...
1 reply by Yahya Mohamed Mohamed Ibrahim
Jun 03, 2025 5:43 AM
Yahya Mohamed Mohamed Ibrahim
...
yes, you are right.
but if it in PMI-SP exam question, what would you choose to answer?
avatar
Yahya Mohamed Mohamed Ibrahim Planning Engineer| AAW
Jun 03, 2025 4:52 AM
Replying to Kiron Bondale
...
In the real world, all of these could result in updates to existing documents such as an Assuptions Log or a Risk Register.

Kiron
yes, you are right.
but if it in PMI-SP exam question, what would you choose to answer?
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada

In that case it would be Define Activities, but because that process updates components of the PM Plan, I'd argue that those are also "Project documents" - this is a long standing issue I have with multiple editions of the PMBOK Guide that haven't come up with a better term than "Project document updates" to cover the "other" documents.

Kiron

avatar
Luis Branco CEO| Business Insight, Consultores de Gestão, Ldª Carcavelos, Lisboa, Portugal
I completely agree that, in practice, almost any process can generate insights that deserve to be captured in documents like the Assumptions Log or the Risk Register.
However, for exam purposes, we go by what is explicitly listed as outputs in the PMBOK Guide.
The distinction between 'Project Documents' and components of the 'Project Management Plan' does create ambiguity — and it remains a poorly resolved gray area across multiple editions of the Guide.
Thanks for raising this, Kiron Bondale .
It's exactly this kind of nuance that separates what’s in the books from what we experience in the real world
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Yahya, in principle, all those could generate changes to project documents but if I have to chose one, I will chose option C “Sequence Activities” because this activity primarily results in updates to the project schedule network diagram and may update project data or outputs, but it typically does not generate changes to project documents.
...
1 reply by Yahya Mohamed Mohamed Ibrahim
Jun 03, 2025 12:48 PM
Yahya Mohamed Mohamed Ibrahim
...
I totally agree with you, but all AI are like the @Kiron Bondale opinion.
so now,
confused where we can get the last decision for a lot of confusing Questions on the ATP Exams simulators?!
avatar
Yahya Mohamed Mohamed Ibrahim Planning Engineer| AAW
Jun 03, 2025 10:15 AM
Replying to Rami Kaibni
...
Yahya, in principle, all those could generate changes to project documents but if I have to chose one, I will chose option C “Sequence Activities” because this activity primarily results in updates to the project schedule network diagram and may update project data or outputs, but it typically does not generate changes to project documents.
I totally agree with you, but all AI are like the @Kiron Bondale opinion.
so now,
confused where we can get the last decision for a lot of confusing Questions on the ATP Exams simulators?!
avatar
Keith Novak Tukwila, Wa, United States
I have found a lot of the practice exam questions that I consider fundamentally flawed. A-D are all part of the Planning Process Group. From Process Groups: A Practice Guide p.77:

A) Estimate Activity Resources (5.16)
B) Estimate Activity Durations (5.9)
C) Sequence Activities (5.8)
D) Define Activities (5.7)

All of those are documented, and not even the wording was changed.

I have found that due to the poor quality of many of the practice questions, there is more value reasoning your way through why it's a bad question than getting an answer that the author of the question intended.
...
1 reply by Yahya Mohamed Mohamed Ibrahim
Jun 04, 2025 12:47 AM
Yahya Mohamed Mohamed Ibrahim
...
I totally agree with you,
I`m confused why PMI agree to this, wasting of time for no reason.
Alot of questions have no sense and when i complain to the trainer he says ' IM ATP of PMI and these questions are approved from PMI!!
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
In general, the real PMI exams will not ask such "straight out of the book" questions. The trend has been to focus more on scenario or application oriented questions.

Kiron
...
1 reply by Yahya Mohamed Mohamed Ibrahim
Jun 04, 2025 12:48 AM
Yahya Mohamed Mohamed Ibrahim
...
Thanks alot Mr Manager Kiron!
avatar
Yahya Mohamed Mohamed Ibrahim Planning Engineer| AAW
Jun 03, 2025 2:01 PM
Replying to Keith Novak
...
I have found a lot of the practice exam questions that I consider fundamentally flawed. A-D are all part of the Planning Process Group. From Process Groups: A Practice Guide p.77:

A) Estimate Activity Resources (5.16)
B) Estimate Activity Durations (5.9)
C) Sequence Activities (5.8)
D) Define Activities (5.7)

All of those are documented, and not even the wording was changed.

I have found that due to the poor quality of many of the practice questions, there is more value reasoning your way through why it's a bad question than getting an answer that the author of the question intended.
I totally agree with you,
I`m confused why PMI agree to this, wasting of time for no reason.
Alot of questions have no sense and when i complain to the trainer he says ' IM ATP of PMI and these questions are approved from PMI!!
avatar
Yahya Mohamed Mohamed Ibrahim Planning Engineer| AAW
Jun 03, 2025 3:22 PM
Replying to Kiron Bondale
...
In general, the real PMI exams will not ask such "straight out of the book" questions. The trend has been to focus more on scenario or application oriented questions.

Kiron
Thanks alot Mr Manager Kiron!