Which of the following does NOT generate changes to the Project documents?

linkedin twitter facebook   Scheduling  
avatar
Yahya Mohamed Mohamed Ibrahim Planning Engineer| AAW
A) Estimate Activity Resources
B) Estimate Activity Durations
C) Sequence Activities
D) Define Activities
Sort By:
< 1 2 >
avatar
VerĂ³nica Elizabeth Pozo Ruiz RYLAI Access Control Quito, Pichincha, Ecuador
Since in the certification questions you have to choose the "best" option, I think the answer that is more accurate is C) Sequence Activities.

Even though all the responses are outputs of the time management knowledge area, the option "Sequence Activities" could be less invasive, since it consists of establishing the relations and order between the activities in the project schedule network diagram.

For the other part, defining activities, estimating activity resources, and estimating durations involve major changes in the respective project documents.
< 1 2 >

Please login or join to reply

Content ID:
ADVERTISEMENTS

Love can sweep you off your feet and carry you along in a way you've never known before. But the ride always ends, and you end up feeling lonely and bitter. Wait. It's not love I'm describing. I'm thinking of a monorail.

- Jack Handey

ADVERTISEMENT

Sponsors