Project Management

Please login or join to subscribe to this thread

Change Control Process. Impact Analysis first or Submit the Change request first?

linkedin twitter facebook   Change Management  
avatar
Mohammad Bozorgzadeh Project Manager| None OTTAWA, ONTARIO, Canada

Hi All, 



I have a question. In PMBOK rev 6 or rev 7, it is not stated clearly what are the initial steps of change request. 



If a change requested, Project manager should first do the impact analysis, then submit the change request, or First, change request must be submitted, then Impact analysis take place? 

Sort By:
avatar
Luis Branco CEO| Business Insight, Consultores de Gestão, Ldª Carcavelos, Lisboa, Portugal

Mohammad Bozorgzadeh
Great question — and a common dilemma in project practice.

The PMBOK Guide (both 6th and 7th editions) does not prescribe a rigid sequence between impact analysis and the formal submission of a change request, because this depends largely on the project's governance structure and the change control system adopted by the organization.

However, there’s a key best practice principle:
- No change should be approved or implemented before its impact is understood.

In mature environments, the process typically unfolds in two stages:
- Preliminary logging of the change request — either informally or via an initial form, simply to document that a change has been proposed and needs evaluation.
- Impact analysis conducted by the PM or technical team — assessing effects on scope, time, cost, quality, risks, etc.
- Formal submission of the request to the CCB (Change Control Board) — now based on solid data and well-founded recommendations.

So, impact analysis occurs before any formal decision to approve the change — but it can be done after the initial registration of the request, even if that request hasn’t yet been formally submitted for approval.

This is also consistent with agile and hybrid governance approaches, where change may emerge iteratively, but is only incorporated into the baseline if it adds value and proves feasible.

Practical Summary:
- First: someone proposes the change →
- Then: PM analyzes impacts →
- Finally: formal submission for decision-making.

Thanks for raising this — it opens space for improving clarity and robustness in how change control is executed in many project environments.

avatar
Mohammad Bozorgzadeh Project Manager| None OTTAWA, ONTARIO, Canada

Thanks Luis for clarifying.



In practice, can we consider it as this?



1. if the change need arises from PM or project team, first, PM must do the assessment and then submit the change request.



2. if the change need arises form different stakeholders (internal or external), they must first formally submit change request, then PM do the assessment and submit the result to the CCB, so they can decide.



avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Mohammad, in a project, all change requests are submitted by the project team so after you identify the change, the PM should perform impact analysis and then submit a formal change request which includes the impact analysis because this analysis will support the decision making of the governance body. There is no point of submitting a change order without an impact analysis.
...
1 reply by Uchechukwu Ozo
Feb 11, 2026 12:59 PM
Uchechukwu Ozo
...
Okay. I came here because I'm trying to pass the CAPM exam, and I understand that real world practices might differ from PMI rules. So please, what does PMI suggest? 😁
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Mohammad -

I'd also suggest that in the real world, the team and potentially other stakeholders would be involved in the impact analysis as the PM is rarely going to have sufficient knowledge across all areas of competency to fully appreciate the impacts to all project variables.

And there might be cases where due to significant constraints a decision-making body such as a change control board or a sponsor might do a first review of a submitted change request to decide if it is even worth the team's effort in performing the impact analysis and would reject those that are not.

Kiron
avatar
Luis Branco CEO| Business Insight, Consultores de Gestão, Ldª Carcavelos, Lisboa, Portugal

Mohammad Bozorgzadeh, your clarification helps refine the scenario — and your distinction is valid as a practical heuristic.
Let me offer a slight refinement that may help generalize the approach while preserving flexibility:

1. When the change originates within the project team or PM:
Yes, in such cases, the PM (or delegated technical lead) usually does a preliminary assessment before escalating the change request.
This ensures that only viable, value-adding proposals are submitted formally.
The impact analysis may be light at this stage, depending on complexity, but it’s often enough to filter out noise or unjustified ideas.

Note: In most cases, the impact analysis is a collaborative effort.
The PM coordinates the assessment, but relies on input from technical leads, financial controllers, schedulers, or other subject-matter experts, depending on the nature of the proposed change.

2. When the change originates from external stakeholders (client, sponsor, users, etc.):
Correct — stakeholders typically must submit a formal or semi-formal change request, especially if it affects contractual scope, cost, or timeline.
Then the PM leads or coordinates the impact analysis, feeding this information into the change control process for decision-making (e.g., via the CCB).

Key Consideration:
What matters most is not who initiates the change, but when the impact analysis happens in relation to the decision.
The impact must precede any approval — even if the initial request was logged earlier for tracking purposes.

Suggested Practice:

Initial Logging: Any proposed change — internal or external — should be captured in a change log or register, even informally.

Impact Analysis: Performed before any decision is made, but can occur after logging and before formal submission.

Formal Submission: Occurs once the impact is known and the request is ready for evaluation by the appropriate governance body (e.g., CCB).

This logic also supports agile and hybrid governance, where change proposals are frequent, but only make it into the product or project baseline after validated learning and impact understanding.

Thanks again for moving the discussion forward — change control is a subtle but powerful discipline!

avatar
Uchechukwu Ozo Wuse, FC, Nigeria
Jun 24, 2025 3:36 PM
Replying to Rami Kaibni
...
Mohammad, in a project, all change requests are submitted by the project team so after you identify the change, the PM should perform impact analysis and then submit a formal change request which includes the impact analysis because this analysis will support the decision making of the governance body. There is no point of submitting a change order without an impact analysis.
Okay. I came here because I'm trying to pass the CAPM exam, and I understand that real world practices might differ from PMI rules. So please, what does PMI suggest? 😁

Please login or join to reply

Content ID:
ADVERTISEMENTS

"Success consists of going from failure to failure without loss of enthusiasm."

- Winston Churchill

ADVERTISEMENT

Sponsors