PMP Q-3 :

linkedin twitter facebook  
avatar
HEMAM RANJIT KUMAR SINGH Founder & Director| TechSure Global Consultancy LLP Guwahati, Assam, India
A Mega construction project is undergoing in the state of Ohio. John represents the Customer for this project. Phillips & Sons LLC is the Contracting Company which is constructing the project. Some packages of the project, viz., the New Sub-Station package has been completed and now about to be handed over to John, which is acceptable as per the Contractual clause. In this situation, to keep construction errors or defects out of the hands of the customer, which is the BEST tools & technique to be employed by the Contractor before handing over the said package:

A. Quality Audit
B. Process analysis
C. Statistical sampling
D. Inspection

(Please note: Self - prepared question and earlier posted in Linkedin Forum. Posted for discussion purposes only)
Sort By:
avatar
anil kukreti Senior engineer | Mobiquity softech pvt ltd Ghaziabad, Uttar Pradesh, India
I think both Statistical sampling and Inspection can be used during Control Quality process but in this case I think inspection is more suitable to keep defects out from hands of customer.

avatar
HEMAM RANJIT KUMAR SINGH Founder & Director| TechSure Global Consultancy LLP Guwahati, Assam, India
Thanks Anil for your attempt. Yes, the Correct answer is Option # D. Inspection

Justification:

Inspection includes activities such as measuring , examining and validating to determine whether the work and deliverables meet requirements and product acceptance criteria.

So, inspection is described as keeping errors out of the hands of the customers. (Reference Page # 250 , Bullet Point # 1 PMBOK Guide 5th Edition)