A project life cycle is the series of phases that a project passes through from its initiation to its closure. With regard to the Stakeholder influences and the Cost of changes in a Project, which is TRUE from the following statements?

A. Predictive Life Cycles are developed with the intent of keeping stakeholder influences higher and the costs of changes lower throughout the Project Life Cycle than in Adaptive Life Cycle.
B. Adaptive Life Cycles, in particular, are developed with the intent of keeping stakeholder influences higher and the costs of changes lower throughout the Project Life Cycle than in Predictive Life Cycle.
C. Both the Life Cycles are developed with the intent of keeping the stakeholder influences high and the costs of changes also high throughout the Project Life Cycle.
D. Adaptive Life Cycles, in particular, are developed with the intent of keeping the costs of changes higher and stakeholder influences also higher throughout the Project Life Cycle than in Predictive Life Cycle.

(Please note: Self - prepared question and earlier posted in Linkedin Forum. Posted for discussion purposes only)
Sort By:
avatar
HEMAM RANJIT KUMAR SINGH Founder & Director| TechSure Global Consultancy LLP Guwahati, Assam, India
hi All,

This is straight from the PMBOK Guide 5th Edition. Any aspirant want to have a try ?

Thanks and best regards,

Ranjit
avatar
Niranjan Pabbathi Technical Program Manager| Akamai Technologies Bangalore, Karnataka, India
Adaptive Life Cycles, in particular, are developed with the intent of keeping stakeholder influences higher and the costs of changes lower throughout the Project Life Cycle than in Predictive Life Cycle.
avatar
NARENDER GUDIBANDA Program Director| Tata Consultancy Services Frisco, Tx, United States
Agile methodology involves higher participation levels of stakeholders in each iteration and thus lower costs of changes in the project. So, answer B is correct.
avatar
Hannes Kropf Project Manager| ITERGO GmbH Hamburg, Hamburg, Germany
Option A) is wrong since the influence of the stakeholder are lower in the predictive life cycle and the cost of changes are higher in the predictive life cycle
Option C) is wrong, because the cost of changes are low in the adaptive life cycle
Option D) is wrong, because the intent is to keep the cost of changes lower in the adaptive life cycle.
Option B) is correct, because Adaptive Life Cycles are developed with the intent of keeping stakeholder influences higher and the costs of changes lower throughout the Project Life Cycle

Option B) is correct.
avatar
PENDYALA VISHWANATH PHANILAL Deputy General Manager Projects| Adani Group Ahmedabad, Gu, India
ANSWER : B