HEMAM RANJIT KUMAR SINGHFounder & Director| TechSure Global Consultancy LLPGuwahati, Assam, India
While preparing for the PMP Exam in a Study Group, Krutika had an argument with Arnab regarding the fundamental relationships of Plan – Do – Check – Act. According to Arnab the “Act” part of this P-D-C-A cycle belongs to the Executing process group, which Krutika disagrees.
Which is TRUE from the following statements, with respect to their discussions?
A. Plan and Act belong to Planning process group
B. Do and Act belong to Executing process group
C. Check and Act belong to Monitoring & Controlling process group.
D. Check and Act belong to Closing process group
(Please note: Self - prepared question and earlier posted in Linkedin Forum. Posted for discussion purposes only)