Liam and Michael are PMP aspirants who are in confusion. According to Liam, Requirements Management Plan is not any of the Subsidiary Plans of Project Management Plan, which Michel disagrees.
What is true about the Requirements Management Plan?
A. It is an output of Plan Requirements Management Process
B. It is an output of Plan Scope Management Process
C. It is an output of Plan Quality Management Process
D. It is an output of Plan Process Improvement Management
Process
(Please note: Self - prepared question and earlier posted in Linkedin Forum. Posted for discussion purposes only)
Saving Changes...
Sort By:
Mohamed RefaatProjects Manager | Toyota & Lexus - QatarDoha, Al Dawha, Qatar
I think B
as the scope management plan describe how scope will be defined and validated and controlled so,requirement management plan is included.