Liam and Michael are PMP aspirants who are in confusion. According to Liam, Requirements Management Plan is not any of the Subsidiary Plans of Project Management Plan, which Michel disagrees.
What is true about the Requirements Management Plan?

A. It is an output of Plan Requirements Management Process
B. It is an output of Plan Scope Management Process
C. It is an output of Plan Quality Management Process
D. It is an output of Plan Process Improvement Management
Process

(Please note: Self - prepared question and earlier posted in Linkedin Forum. Posted for discussion purposes only)


Sort By:
avatar
Mohamed Refaat Projects Manager | Toyota & Lexus - Qatar Doha, Al Dawha, Qatar
I think B
as the scope management plan describe how scope will be defined and validated and controlled so,requirement management plan is included.

I hope to be right??
avatar
anil kukreti Senior engineer | Mobiquity softech pvt ltd Ghaziabad, Uttar Pradesh, India
B.

Justification : Outputs of Plan Scope Management process are Requirements Management Plan and Scope Management Plan.

avatar
HEMAM RANJIT KUMAR SINGH Founder & Director| TechSure Global Consultancy LLP Guwahati, Assam, India
Both Mohamed and Anil responded correctly. Yes, the correct answer is Option # B. It is an output of Plan Scope Management Process

(Reference Page # 107 Para 5.1 PMBOK Guide 5th Edition)

Thanks and best regards,

Ranjit
avatar
Kalyan Parihari Gurugram, India
yes, It is 'B"