Mohamed basheerMOHAMED BASHEER,PMP®,PMI-SP®| Planning Manager, JASARA PMCJeddah, Saudi Arabia
One of your project has completed today with a planned value of $200,000. What is the schedule variance of the project now?
a) One
b) Cannot be determined
c) Zero
d) $200,000 Saving Changes...
Ahmed FathySenior Manager, Enterprise Project Management Office| Department of Education, Northern Territory GovernmentDarwin, Northern Territory, Australia
b) Cannot be determined
As the schedule variance is a comparison between schedule baseline and actual. In this question you have the finish date but the schedule end date is missing so you can't determine if it was finished on-time or not.