One of your project has completed today with a planned value of $200,000. What is the schedule variance of the project now?
a) One
b) Cannot be determined
c) Zero
d) $200,000
avatar
Ahmed Fathy Senior Manager, Enterprise Project Management Office| Department of Education, Northern Territory Government Darwin, Northern Territory, Australia
b) Cannot be determined

As the schedule variance is a comparison between schedule baseline and actual. In this question you have the finish date but the schedule end date is missing so you can't determine if it was finished on-time or not.

Thanks
Ahmed