Aejaz ShaikhPM I| Alyx Technologies India Pvt LtdPune, Maharshatra, India
Plan Stakeholder Management - Outputs illustrates that Project Schedule document can get updated. Under what circumstances or scenarios Project Schedules will change/get updated Saving Changes...
Sort By:
Rao Vasudeva GProgram Manager| Aeronautical Development AgencyBangalore, Karnataka, India
Managing stakeholders is a very complex and sensitive;, requires great analysis sense of their interest, influence and power, otherwise project suffers from schedule, cost and other factors
There are few reasons
When Scope is changed by the stakeholders.
Delay in taking decision on change requests.
Some of stakeholders are not supporting the team for technical issues
Powered stakeholder is not resistant to change
Ambiguity requirements from a stakeholder that may leads to rework
Saving Changes...
Thomas WalentaGlobal Project Economy ExpertHackenheim, Germany
In the context of the PMBoK process 'plan stakeholder management' I believe the schedule might be updated in particular if you identify new communication tasks to stakeholders.
For example, you might find it necessary to deliver a monthly newsletter and then you have to schedule and cost it. Or you may at certain intervals invite to allhand project information sessions. Or assign team members to cover key stakeholders, with checkpoints in the schedule. Or engage a marketing agent to present your project, until xx.xx.xxxx. Saving Changes...