Practice_Question_5

linkedin twitter facebook  
avatar
saurabh mahajan PMP, ITIL, PRINCE2| vodafone Pune, Maharashtra, India
Rahul is currently working on preparing the project management plan. He suddenly realizes that some of the parameters for planning are changing and thus impacting the management plan. This might impact subsequent project execution as well. Rahul decides to wait till all the inputs to project management plan are finalized. However this will impact seriously to the project schedule. What should Rahul do in this situation?

a) Rahul is concerned about the correct and stable inputs for the management plan and hence has wisely decided to wait till everything is sorted.
b) Rahul should be aware that development of the project management plan is an iterative activity and is progressively elaborated throughout the project’s life cycle.
c) Rahul should hold a meeting with all stakeholders to raise this issue and get the resolution in the meeting to save on time as this looks a communication gap.
d) Rahul should contact senior management to get it pushed from higher level.
Sort By:
avatar
Bala S Duvvuri Project Manager| Shell Bangalore, Karnataka, India
I think answer should be B
avatar
Ebenezer Daramola Manager| Ebensoft Consulting Ltd London, United Kingdom
b) Rahul should be aware that development of the project management plan is an iterative activity and is progressively elaborated throughout the project’s life cycle.
avatar
MAEN QADDOURAH Project Director| AJ SAUDI Jeddah, Saudi Arabia
B is correct answer
avatar
Alfonso Trujillo Oakville, Ontario, Canada
I agree, B is the most correct answer.
D is not completely wrong if it read ¨Sponsor¨instead of ¨senior management¨
avatar
Stéphane Parent Self Employed / Semi-retired| Leader Maker Prince Edward Island, Canada
B too