saurabh mahajanPMP, ITIL, PRINCE2| vodafonePune, Maharashtra, India
Rahul is currently working on preparing the project management plan. He suddenly realizes that some of the parameters for planning are changing and thus impacting the management plan. This might impact subsequent project execution as well. Rahul decides to wait till all the inputs to project management plan are finalized. However this will impact seriously to the project schedule. What should Rahul do in this situation?
a) Rahul is concerned about the correct and stable inputs for the management plan and hence has wisely decided to wait till everything is sorted.
b) Rahul should be aware that development of the project management plan is an iterative activity and is progressively elaborated throughout the project’s life cycle.
c) Rahul should hold a meeting with all stakeholders to raise this issue and get the resolution in the meeting to save on time as this looks a communication gap.
d) Rahul should contact senior management to get it pushed from higher level. Saving Changes...
Sort By:
Bala S DuvvuriProject Manager| ShellBangalore, Karnataka, India
I think answer should be B Saving Changes...
Ebenezer DaramolaManager| Ebensoft Consulting LtdLondon, United Kingdom
b) Rahul should be aware that development of the project management plan is an iterative activity and is progressively elaborated throughout the project’s life cycle. Saving Changes...
MAEN QADDOURAHProject Director| AJ SAUDIJeddah, Saudi Arabia