MS Project Question--umbrella tasks

linkedin twitter facebook  
avatar
Paul Bibler PMP Bartlett, Il, United States
I'm trying to set up an umbrella task in Project 2000. I want it to start when the project starts, and end when the project ends. I have heard the term "hammock" for these tasks as well. I was able to do this in P3, but I can't figure it out in Project2000, nor can anyone I work with. Any ideas? Thanks in advance.
Sort By:
avatar
Jeanine McGuire Jacksonville, Fl, United States
Paul,

I haven't been able to accomplish this either. I've worked around it with milestone tasks to indicate the project start and end dates. When you include these tasks under the umbrella task, the dates of the umbrella task reflect the start and end of the project.
avatar
Anonymous
see if the following provides any help:
http://www.mvps.org/project/faqs.htm#Hammock Tasks
avatar
Paul Bibler PMP Bartlett, Il, United States
Rich,



That seems to work, just what I was looking for. Thanks for the tip.

Please login or join to reply

Content ID:
ADVERTISEMENTS

"In Italy for thirty years under the Borgias they had warfare, terror, murder, bloodshed - but they produced Michelangelo, Leonardo da Vinci, and the Renaissance. In Switzerland they had brotherly love, 500 years of democracy and peace, and what did that produce? The cuckoo clock."

- Orson Welles, The Third Man

ADVERTISEMENT

Sponsors