Lea BongiovanniProject Manager| ConfidentialPhiladelphia, Pa, United States
Can anyone tell me how to prevent Estimated Work Hours from changing when entering Actual Work hours for a resource in Project Server?
For example: I estimated that Richard would work 172.5 hours in November. But Richard actually worked 150 hours. I enter 150 hours under Actual Work Hours and the Estimated Work Hours changes to 150. I need that number to remain as 172.5 so that at the end year and I'm reporting projected vs. actuals - I can have a record of what was initially estimated.
One possible solution I thought about was creating a Baseline Work Hours.
Please let me know if any additional information is needed. Saving Changes...