MS Project Tracking Reports

linkedin twitter facebook  
avatar
Diane Mair IT Manager| Allegis Group Bowie, Md, United States
In an MS Project plan, we have created a filter on the Gantt view that displays tasks that should have been completed by a certain date but are not marked as 100% complete. For the lowest level tasks, this view works perfectly - showing us actual hours, planned hours, and remaining work. The problem exists at the summary levels. The summary tasks show hours for all subtasks, including those that do not meet the filtered criteria. What is the optimal way to summarize the data, but only for tasks that meet the criteria of the filter?

Thanks in advance

Please login or join to reply