What is a typical estimation ratio, ‘Estimated PM engagement hours /Total Estimated Project hours’ you use in your industry for the below. What is PMI standard or recommendation?

linkedin twitter facebook  
avatar
Saroj Bajpai PhD Dr| CHI Omaha, Ne, United States
Example What would you use if it’s a 5000 hours project of medium complexity, 5-6 Vendors involved, > 5 teams (2 members minimum) to be completed in 6 months?

1. Complex Enterprise Project with >10 functional areas, Multiple Markets/Regions in US >5 Teams of various sizes (2-10), >5 vendors, Testing, interfaces and Integration involved.

2. Medium Complexity Project

Please mention framework you use for the estimation.
Sort By:
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
The rate is 20%-25% of total project duration. But with that say you will find that it will depends on a lot of factors where the most important is organizational maturity about project management.
avatar
Paolo Cornali Project Manager| HTA srl Brescia, Lombardia, Italy
I agree with Sergio.
A typical rate of 20% is used. 30% for complex project.
avatar
Markus Kopko AI Enabler for Project & Program Mgmt | Founder PMotion.ai / The PM AI Coach| PMotion.ai Hamburg, Hamburg, Germany
Sergio is on point (as usual),
it depends heavily on the organizations maturity level in project management.
If organization is on a lower level than the ratio could be at 40% and more easily.
15 - 25% is usual in our industry/company (IT Outsourcing).

Regards,

Markus
...
1 reply by Sergio Luis Conte
Feb 22, 2016 6:24 AM
Sergio Luis Conte
...
Thank you very much for your feedback Marcus. I spend my time in this type of forums to improve myself for other comments. Like your comments no matter we agree or not.
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Feb 22, 2016 3:09 AM
Replying to Markus Kopko
...
Sergio is on point (as usual),
it depends heavily on the organizations maturity level in project management.
If organization is on a lower level than the ratio could be at 40% and more easily.
15 - 25% is usual in our industry/company (IT Outsourcing).

Regards,

Markus
Thank you very much for your feedback Marcus. I spend my time in this type of forums to improve myself for other comments. Like your comments no matter we agree or not.