Hi All,
Thanks for the replies.
Hi Darren,
That is what my expectation is. I had a good argument with someone that once the scope is agreed between both parties..in the case of example where customer stated he needed a wooden box only and the requirements are signed, for what ever change there after I will follow the Change Management process without fail post my scope baseline is agreed between both parties.
But the other project manager told me that as a Customer he will not agree to pay more for the additional work (Shelves within the box) as he felt that it is covered in signed baseline.
Hope my assumption is valid