I have a project with three interconnected work group efforts. One is on a 24x7 schedule and the other two on 8x5 workdays. Changing one group to 24x7 forces all groups to go to that figure. I am using MS Project 98. Is there a way around this or does 2000 or 2002 allow different workday settings? Saving Changes...