I am also interested in the functionality of these add-on. Why are they important? Which gap do they cover? Saving Changes...
Patrick DiceyManager, Customer Project Management| CentralSquare TechnologiesOrlando, Fl, United States
A few add-ons I've used: Schedule Risk Assessment (probabilistic/monte carlo), IMS Health Check (DCMA 14 point), Summary Schedule Generators, and Integrated Program Management Report (IMPR) Format 6 UNCEFACT XML Generator. Saving Changes...