Project Management

Please login or join to subscribe to this thread

any one having the PM formulas list?

linkedin twitter facebook  
avatar
Sajish G Das India
I wish to know the PM Formulas
Sort By:
< 1 2 3 >
avatar
Markus Kopko AI Enabler for Project & Program Mgmt | Founder PMotion.ai / The PM AI Coach| PMotion.ai Hamburg, Hamburg, Germany
Earned Value
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
EAC ‘variances will remain’ = BAC / CPI
EAC ‘fundamentally flawed’ = AC + Bottom-up ETC
EAC ‘variance will not happen again’ = AC + BAC – EV
EAC ‘over budget + deadline’ = AC + [(BAC - EV) / (CPI * SPI)]
ETC = EAC - AC
ETC ‘flawed’ = new estimate
ETC ‘unearned budget’ = BAC - EV
ETC ‘over budget + deadline’ = ETC = (BAC - EV) / (CPI * SPI)
ETC ‘variances will remain’ = (BAC / CPI) - AC
Percent Complete = EV / BAC * 100
VAC = BAC - EAC
EV = % complete * BAC
TCPI ‘based on BAC’ = (BAC – EV) / (BAC – AC)
TCPI ‘based on EAC’ = (BAC – EV) / (EAC – AC)

PERT
PERT Beta 3-point = (Pessimistic + (4 * Most Likely) + Optimistic) / 6
PERT Triangular 3-point = (Pessimistic + Most Likely + Optimistic) / 3
PERT ? = (Pessimistic - Optimistic) / 6
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2
PERT Deviation all activities = ?sum((Pessimistic - Optimistic) / 6)^2

Communications
Communication Channels = n * (n-1) / 2

Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost

Probability
EMV = Probability * Impact in currency

Network Diagram
Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1
Total Float = LS - ES or Total Float = LF – EF
Free Float = ES of Following - ES of Present - DUR of Present
EF = ES + duration - 1
ES = EF of predecessor + 1
LF = LS of successor - 1
LS = LF - duration + 1

Project Selection
PV = FV / (1+r)^n
FV = PV * (1+r)^n
NPV = Select biggest number. (Formula not required for exam)
ROI = Select biggest number. (Formula not required for exam)
IRR = Select biggest number. (Formula not required for exam)
Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment.
BCR = Benefit / Cost
CBR = Cost / Benefit
Opportunity Cost = The value of the project not chosen.

Depreciation
Straight-line Depreciation:
Depr. Expense = (Asset Cost – Scrap Value) / Useful Life
Depr. Rate = 100% / Useful Life
Double Declining Balance Method:
Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
...
3 replies by Anupam , Rami Kaibni, and Sajish G Das
Sep 16, 2016 2:32 AM
Sajish G Das
...
Thank you Markus.
Sep 16, 2016 5:13 AM
Anupam
...
Thanks for sharing Markus, that's a long list. It reminded me of my exam days, though in actual test, I didn't see most of it.
Sep 16, 2016 4:51 PM
Rami Kaibni
...
Markus, As usual, very impressive and detailed feedback. I hope you are doing well.
avatar
Sajish G Das India
Sep 16, 2016 2:25 AM
Replying to Markus Kopko
...
Earned Value
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
EAC ‘variances will remain’ = BAC / CPI
EAC ‘fundamentally flawed’ = AC + Bottom-up ETC
EAC ‘variance will not happen again’ = AC + BAC – EV
EAC ‘over budget + deadline’ = AC + [(BAC - EV) / (CPI * SPI)]
ETC = EAC - AC
ETC ‘flawed’ = new estimate
ETC ‘unearned budget’ = BAC - EV
ETC ‘over budget + deadline’ = ETC = (BAC - EV) / (CPI * SPI)
ETC ‘variances will remain’ = (BAC / CPI) - AC
Percent Complete = EV / BAC * 100
VAC = BAC - EAC
EV = % complete * BAC
TCPI ‘based on BAC’ = (BAC – EV) / (BAC – AC)
TCPI ‘based on EAC’ = (BAC – EV) / (EAC – AC)

PERT
PERT Beta 3-point = (Pessimistic + (4 * Most Likely) + Optimistic) / 6
PERT Triangular 3-point = (Pessimistic + Most Likely + Optimistic) / 3
PERT ? = (Pessimistic - Optimistic) / 6
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2
PERT Deviation all activities = ?sum((Pessimistic - Optimistic) / 6)^2

Communications
Communication Channels = n * (n-1) / 2

Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost

Probability
EMV = Probability * Impact in currency

Network Diagram
Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1
Total Float = LS - ES or Total Float = LF – EF
Free Float = ES of Following - ES of Present - DUR of Present
EF = ES + duration - 1
ES = EF of predecessor + 1
LF = LS of successor - 1
LS = LF - duration + 1

Project Selection
PV = FV / (1+r)^n
FV = PV * (1+r)^n
NPV = Select biggest number. (Formula not required for exam)
ROI = Select biggest number. (Formula not required for exam)
IRR = Select biggest number. (Formula not required for exam)
Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment.
BCR = Benefit / Cost
CBR = Cost / Benefit
Opportunity Cost = The value of the project not chosen.

Depreciation
Straight-line Depreciation:
Depr. Expense = (Asset Cost – Scrap Value) / Useful Life
Depr. Rate = 100% / Useful Life
Double Declining Balance Method:
Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
Thank you Markus.
...
1 reply by Markus Kopko
Sep 16, 2016 2:34 AM
Markus Kopko
...
You are welcome, please do not hesitate to ask any further question especially to the PMP certification and also to all the other PMI certifications.
I am glad if i could be of help.

Regards,

Markus
avatar
Markus Kopko AI Enabler for Project & Program Mgmt | Founder PMotion.ai / The PM AI Coach| PMotion.ai Hamburg, Hamburg, Germany
Sep 16, 2016 2:32 AM
Replying to Sajish G Das
...
Thank you Markus.
You are welcome, please do not hesitate to ask any further question especially to the PMP certification and also to all the other PMI certifications.
I am glad if i could be of help.

Regards,

Markus
avatar
Anupam India
Good to know -

6 sigma : 99.99%
3 sigma : 99.73%
2 sigma : 95.46%
1 sigma : 68.26%


Pareto : 80/20 Rule

Body Language: 7% words, 38% Tonality, 55% Non Verbal

Order of Magnitude -25% to +75%
Conceptual -30% to +50%
Preliminary -20% to +30%
Definitive -5% to +10%
Control -10% to +15%
...
1 reply by Markus Kopko
Sep 19, 2016 3:36 AM
Markus Kopko
...
thanks Anupam for the complementary formulas

havn't include them to not overload the information ;) ... but of course this is also useful and important
avatar
Anupam India
Sep 16, 2016 2:25 AM
Replying to Markus Kopko
...
Earned Value
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
EAC ‘variances will remain’ = BAC / CPI
EAC ‘fundamentally flawed’ = AC + Bottom-up ETC
EAC ‘variance will not happen again’ = AC + BAC – EV
EAC ‘over budget + deadline’ = AC + [(BAC - EV) / (CPI * SPI)]
ETC = EAC - AC
ETC ‘flawed’ = new estimate
ETC ‘unearned budget’ = BAC - EV
ETC ‘over budget + deadline’ = ETC = (BAC - EV) / (CPI * SPI)
ETC ‘variances will remain’ = (BAC / CPI) - AC
Percent Complete = EV / BAC * 100
VAC = BAC - EAC
EV = % complete * BAC
TCPI ‘based on BAC’ = (BAC – EV) / (BAC – AC)
TCPI ‘based on EAC’ = (BAC – EV) / (EAC – AC)

PERT
PERT Beta 3-point = (Pessimistic + (4 * Most Likely) + Optimistic) / 6
PERT Triangular 3-point = (Pessimistic + Most Likely + Optimistic) / 3
PERT ? = (Pessimistic - Optimistic) / 6
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2
PERT Deviation all activities = ?sum((Pessimistic - Optimistic) / 6)^2

Communications
Communication Channels = n * (n-1) / 2

Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost

Probability
EMV = Probability * Impact in currency

Network Diagram
Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1
Total Float = LS - ES or Total Float = LF – EF
Free Float = ES of Following - ES of Present - DUR of Present
EF = ES + duration - 1
ES = EF of predecessor + 1
LF = LS of successor - 1
LS = LF - duration + 1

Project Selection
PV = FV / (1+r)^n
FV = PV * (1+r)^n
NPV = Select biggest number. (Formula not required for exam)
ROI = Select biggest number. (Formula not required for exam)
IRR = Select biggest number. (Formula not required for exam)
Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment.
BCR = Benefit / Cost
CBR = Cost / Benefit
Opportunity Cost = The value of the project not chosen.

Depreciation
Straight-line Depreciation:
Depr. Expense = (Asset Cost – Scrap Value) / Useful Life
Depr. Rate = 100% / Useful Life
Double Declining Balance Method:
Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
Thanks for sharing Markus, that's a long list. It reminded me of my exam days, though in actual test, I didn't see most of it.
...
1 reply by Markus Kopko
Sep 19, 2016 3:40 AM
Markus Kopko
...
;)
btw.: you can find a complete formula study guide with detailed explanations and sample for each formula here:

Formular Study Guide:
? http://goo.gl/l0RFj8

Regards,

Markus
avatar
Drew Craig Sr. Agile & Product Coach| Vanguard Philadelphia, Pa, United States
The action of writing them down (multiple times; old fashion pencil and paper!) will help you to remember.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Sep 16, 2016 2:25 AM
Replying to Markus Kopko
...
Earned Value
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
EAC ‘variances will remain’ = BAC / CPI
EAC ‘fundamentally flawed’ = AC + Bottom-up ETC
EAC ‘variance will not happen again’ = AC + BAC – EV
EAC ‘over budget + deadline’ = AC + [(BAC - EV) / (CPI * SPI)]
ETC = EAC - AC
ETC ‘flawed’ = new estimate
ETC ‘unearned budget’ = BAC - EV
ETC ‘over budget + deadline’ = ETC = (BAC - EV) / (CPI * SPI)
ETC ‘variances will remain’ = (BAC / CPI) - AC
Percent Complete = EV / BAC * 100
VAC = BAC - EAC
EV = % complete * BAC
TCPI ‘based on BAC’ = (BAC – EV) / (BAC – AC)
TCPI ‘based on EAC’ = (BAC – EV) / (EAC – AC)

PERT
PERT Beta 3-point = (Pessimistic + (4 * Most Likely) + Optimistic) / 6
PERT Triangular 3-point = (Pessimistic + Most Likely + Optimistic) / 3
PERT ? = (Pessimistic - Optimistic) / 6
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2
PERT Deviation all activities = ?sum((Pessimistic - Optimistic) / 6)^2

Communications
Communication Channels = n * (n-1) / 2

Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost

Probability
EMV = Probability * Impact in currency

Network Diagram
Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1
Total Float = LS - ES or Total Float = LF – EF
Free Float = ES of Following - ES of Present - DUR of Present
EF = ES + duration - 1
ES = EF of predecessor + 1
LF = LS of successor - 1
LS = LF - duration + 1

Project Selection
PV = FV / (1+r)^n
FV = PV * (1+r)^n
NPV = Select biggest number. (Formula not required for exam)
ROI = Select biggest number. (Formula not required for exam)
IRR = Select biggest number. (Formula not required for exam)
Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment.
BCR = Benefit / Cost
CBR = Cost / Benefit
Opportunity Cost = The value of the project not chosen.

Depreciation
Straight-line Depreciation:
Depr. Expense = (Asset Cost – Scrap Value) / Useful Life
Depr. Rate = 100% / Useful Life
Double Declining Balance Method:
Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
Markus, As usual, very impressive and detailed feedback. I hope you are doing well.
...
1 reply by Markus Kopko
Sep 19, 2016 3:38 AM
Markus Kopko
...
Hi Rami,

thanks for the compliment.
Yes, i am doing well thanks for asking. I hope you to.
Just a bit to much to do the last weeks/months, so i can't contribute here as much as i want to.
But i do have something very nice in the pipeline for projectmanagement. com. I guess it will take part and start of in the beginning of the next year ... we will see ... ;)

Regards,

Markus
avatar
Praveen Malik Independent Consultant| Independent Consultant New Delhi, India
Hi All,

You can download a pdf copy of PMP formulas pocket guide here - http://www.pmbypm.com/download-pmp-formulas-guide-2/

In addition, to understand the formulas, you can look at
1. Earned value management - Click the link to study and understand all the Earned Value Management Formulas (http://www.pmbypm.com/earned-value-management-formulas/)
2. Estimation - Click the link to study and understand all the estimation formulas (http://www.pmbypm.com/three-point-estimate-formulas/)
3. Procurement & Contract types - Click the link to study and understand all the procurement formulas (http://www.pmbypm.com/pmp-formulas-contract-types/)

BR
...
1 reply by Rami Kaibni
Sep 19, 2016 11:20 AM
Rami Kaibni
...
Praveen,

The first link opened but I could not download the guide. Maybe you can guide us through this.

As for the other two links, they opened and the pages showed error.
avatar
Elizabeth Harrin Director| RebelsGuideToPM.com London, England, United Kingdom
I agree that the act of writing them down will help you remember them, so even if you use the lists here, make your own version to help your studies.
...
1 reply by Khaled Al Kolfat
Oct 04, 2016 7:13 AM
Khaled Al Kolfat
...
strongly agree
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Amen, Markus (hehehehehe). Thank you very much for sharing.
...
1 reply by Markus Kopko
Sep 19, 2016 3:39 AM
Markus Kopko
...
You are welcome, Sergio.
< 1 2 3 >

Please login or join to reply

Content ID:
ADVERTISEMENTS

"In the real world, the right thing never happens in the right place and the right time. It is the job of journalists and historians to make it appear that it has."

- Mark Twain

ADVERTISEMENT

Sponsors