any one having the PM formulas list?

linkedin twitter facebook  
avatar
Sajish G Das India
I wish to know the PM Formulas
Sort By:
< 1 2 3 >
avatar
Markus Kopko AI Enabler for Project & Program Mgmt | Founder PMotion.ai / The PM AI Coach| PMotion.ai Hamburg, Hamburg, Germany
Earned Value
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
EAC ‘variances will remain’ = BAC / CPI
EAC ‘fundamentally flawed’ = AC + Bottom-up ETC
EAC ‘variance will not happen again’ = AC + BAC – EV
EAC ‘over budget + deadline’ = AC + [(BAC - EV) / (CPI * SPI)]
ETC = EAC - AC
ETC ‘flawed’ = new estimate
ETC ‘unearned budget’ = BAC - EV
ETC ‘over budget + deadline’ = ETC = (BAC - EV) / (CPI * SPI)
ETC ‘variances will remain’ = (BAC / CPI) - AC
Percent Complete = EV / BAC * 100
VAC = BAC - EAC
EV = % complete * BAC
TCPI ‘based on BAC’ = (BAC – EV) / (BAC – AC)
TCPI ‘based on EAC’ = (BAC – EV) / (EAC – AC)

PERT
PERT Beta 3-point = (Pessimistic + (4 * Most Likely) + Optimistic) / 6
PERT Triangular 3-point = (Pessimistic + Most Likely + Optimistic) / 3
PERT ? = (Pessimistic - Optimistic) / 6
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2
PERT Deviation all activities = ?sum((Pessimistic - Optimistic) / 6)^2

Communications
Communication Channels = n * (n-1) / 2

Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost

Probability
EMV = Probability * Impact in currency

Network Diagram
Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1
Total Float = LS - ES or Total Float = LF – EF
Free Float = ES of Following - ES of Present - DUR of Present
EF = ES + duration - 1
ES = EF of predecessor + 1
LF = LS of successor - 1
LS = LF - duration + 1

Project Selection
PV = FV / (1+r)^n
FV = PV * (1+r)^n
NPV = Select biggest number. (Formula not required for exam)
ROI = Select biggest number. (Formula not required for exam)
IRR = Select biggest number. (Formula not required for exam)
Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment.
BCR = Benefit / Cost
CBR = Cost / Benefit
Opportunity Cost = The value of the project not chosen.

Depreciation
Straight-line Depreciation:
Depr. Expense = (Asset Cost – Scrap Value) / Useful Life
Depr. Rate = 100% / Useful Life
Double Declining Balance Method:
Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
...
3 replies by Anupam , Rami Kaibni, and Sajish G Das
Sep 16, 2016 2:32 AM
Sajish G Das
...
Thank you Markus.
Sep 16, 2016 5:13 AM
Anupam
...
Thanks for sharing Markus, that's a long list. It reminded me of my exam days, though in actual test, I didn't see most of it.
Sep 16, 2016 4:51 PM
Rami Kaibni
...
Markus, As usual, very impressive and detailed feedback. I hope you are doing well.
avatar
Sajish G Das India
Sep 16, 2016 2:25 AM
Replying to Markus Kopko
...
Earned Value
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
EAC ‘variances will remain’ = BAC / CPI
EAC ‘fundamentally flawed’ = AC + Bottom-up ETC
EAC ‘variance will not happen again’ = AC + BAC – EV
EAC ‘over budget + deadline’ = AC + [(BAC - EV) / (CPI * SPI)]
ETC = EAC - AC
ETC ‘flawed’ = new estimate
ETC ‘unearned budget’ = BAC - EV
ETC ‘over budget + deadline’ = ETC = (BAC - EV) / (CPI * SPI)
ETC ‘variances will remain’ = (BAC / CPI) - AC
Percent Complete = EV / BAC * 100
VAC = BAC - EAC
EV = % complete * BAC
TCPI ‘based on BAC’ = (BAC – EV) / (BAC – AC)
TCPI ‘based on EAC’ = (BAC – EV) / (EAC – AC)

PERT
PERT Beta 3-point = (Pessimistic + (4 * Most Likely) + Optimistic) / 6
PERT Triangular 3-point = (Pessimistic + Most Likely + Optimistic) / 3
PERT ? = (Pessimistic - Optimistic) / 6
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2
PERT Deviation all activities = ?sum((Pessimistic - Optimistic) / 6)^2

Communications
Communication Channels = n * (n-1) / 2

Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost

Probability
EMV = Probability * Impact in currency

Network Diagram
Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1
Total Float = LS - ES or Total Float = LF – EF
Free Float = ES of Following - ES of Present - DUR of Present
EF = ES + duration - 1
ES = EF of predecessor + 1
LF = LS of successor - 1
LS = LF - duration + 1

Project Selection
PV = FV / (1+r)^n
FV = PV * (1+r)^n
NPV = Select biggest number. (Formula not required for exam)
ROI = Select biggest number. (Formula not required for exam)
IRR = Select biggest number. (Formula not required for exam)
Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment.
BCR = Benefit / Cost
CBR = Cost / Benefit
Opportunity Cost = The value of the project not chosen.

Depreciation
Straight-line Depreciation:
Depr. Expense = (Asset Cost – Scrap Value) / Useful Life
Depr. Rate = 100% / Useful Life
Double Declining Balance Method:
Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
Thank you Markus.
...
1 reply by Markus Kopko
Sep 16, 2016 2:34 AM
Markus Kopko
...
You are welcome, please do not hesitate to ask any further question especially to the PMP certification and also to all the other PMI certifications.
I am glad if i could be of help.

Regards,

Markus
avatar
Markus Kopko AI Enabler for Project & Program Mgmt | Founder PMotion.ai / The PM AI Coach| PMotion.ai Hamburg, Hamburg, Germany
Sep 16, 2016 2:32 AM
Replying to Sajish G Das
...
Thank you Markus.
You are welcome, please do not hesitate to ask any further question especially to the PMP certification and also to all the other PMI certifications.
I am glad if i could be of help.

Regards,

Markus
avatar
Anupam India
Good to know -

6 sigma : 99.99%
3 sigma : 99.73%
2 sigma : 95.46%
1 sigma : 68.26%


Pareto : 80/20 Rule

Body Language: 7% words, 38% Tonality, 55% Non Verbal

Order of Magnitude -25% to +75%
Conceptual -30% to +50%
Preliminary -20% to +30%
Definitive -5% to +10%
Control -10% to +15%
...
1 reply by Markus Kopko
Sep 19, 2016 3:36 AM
Markus Kopko
...
thanks Anupam for the complementary formulas

havn't include them to not overload the information ;) ... but of course this is also useful and important
avatar
Anupam India
Sep 16, 2016 2:25 AM
Replying to Markus Kopko
...
Earned Value
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
EAC ‘variances will remain’ = BAC / CPI
EAC ‘fundamentally flawed’ = AC + Bottom-up ETC
EAC ‘variance will not happen again’ = AC + BAC – EV
EAC ‘over budget + deadline’ = AC + [(BAC - EV) / (CPI * SPI)]
ETC = EAC - AC
ETC ‘flawed’ = new estimate
ETC ‘unearned budget’ = BAC - EV
ETC ‘over budget + deadline’ = ETC = (BAC - EV) / (CPI * SPI)
ETC ‘variances will remain’ = (BAC / CPI) - AC
Percent Complete = EV / BAC * 100
VAC = BAC - EAC
EV = % complete * BAC
TCPI ‘based on BAC’ = (BAC – EV) / (BAC – AC)
TCPI ‘based on EAC’ = (BAC – EV) / (EAC – AC)

PERT
PERT Beta 3-point = (Pessimistic + (4 * Most Likely) + Optimistic) / 6
PERT Triangular 3-point = (Pessimistic + Most Likely + Optimistic) / 3
PERT ? = (Pessimistic - Optimistic) / 6
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2
PERT Deviation all activities = ?sum((Pessimistic - Optimistic) / 6)^2

Communications
Communication Channels = n * (n-1) / 2

Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost

Probability
EMV = Probability * Impact in currency

Network Diagram
Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1
Total Float = LS - ES or Total Float = LF – EF
Free Float = ES of Following - ES of Present - DUR of Present
EF = ES + duration - 1
ES = EF of predecessor + 1
LF = LS of successor - 1
LS = LF - duration + 1

Project Selection
PV = FV / (1+r)^n
FV = PV * (1+r)^n
NPV = Select biggest number. (Formula not required for exam)
ROI = Select biggest number. (Formula not required for exam)
IRR = Select biggest number. (Formula not required for exam)
Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment.
BCR = Benefit / Cost
CBR = Cost / Benefit
Opportunity Cost = The value of the project not chosen.

Depreciation
Straight-line Depreciation:
Depr. Expense = (Asset Cost – Scrap Value) / Useful Life
Depr. Rate = 100% / Useful Life
Double Declining Balance Method:
Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
Thanks for sharing Markus, that's a long list. It reminded me of my exam days, though in actual test, I didn't see most of it.
...
1 reply by Markus Kopko
Sep 19, 2016 3:40 AM
Markus Kopko
...
;)
btw.: you can find a complete formula study guide with detailed explanations and sample for each formula here:

Formular Study Guide:
? http://goo.gl/l0RFj8

Regards,

Markus
avatar
Drew Craig Sr. Agile & Product Coach| Vanguard Philadelphia, Pa, United States
The action of writing them down (multiple times; old fashion pencil and paper!) will help you to remember.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Sep 16, 2016 2:25 AM
Replying to Markus Kopko
...
Earned Value
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
EAC ‘variances will remain’ = BAC / CPI
EAC ‘fundamentally flawed’ = AC + Bottom-up ETC
EAC ‘variance will not happen again’ = AC + BAC – EV
EAC ‘over budget + deadline’ = AC + [(BAC - EV) / (CPI * SPI)]
ETC = EAC - AC
ETC ‘flawed’ = new estimate
ETC ‘unearned budget’ = BAC - EV
ETC ‘over budget + deadline’ = ETC = (BAC - EV) / (CPI * SPI)
ETC ‘variances will remain’ = (BAC / CPI) - AC
Percent Complete = EV / BAC * 100
VAC = BAC - EAC
EV = % complete * BAC
TCPI ‘based on BAC’ = (BAC – EV) / (BAC – AC)
TCPI ‘based on EAC’ = (BAC – EV) / (EAC – AC)

PERT
PERT Beta 3-point = (Pessimistic + (4 * Most Likely) + Optimistic) / 6
PERT Triangular 3-point = (Pessimistic + Most Likely + Optimistic) / 3
PERT ? = (Pessimistic - Optimistic) / 6
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2
PERT Deviation all activities = ?sum((Pessimistic - Optimistic) / 6)^2

Communications
Communication Channels = n * (n-1) / 2

Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost

Probability
EMV = Probability * Impact in currency

Network Diagram
Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1
Total Float = LS - ES or Total Float = LF – EF
Free Float = ES of Following - ES of Present - DUR of Present
EF = ES + duration - 1
ES = EF of predecessor + 1
LF = LS of successor - 1
LS = LF - duration + 1

Project Selection
PV = FV / (1+r)^n
FV = PV * (1+r)^n
NPV = Select biggest number. (Formula not required for exam)
ROI = Select biggest number. (Formula not required for exam)
IRR = Select biggest number. (Formula not required for exam)
Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment.
BCR = Benefit / Cost
CBR = Cost / Benefit
Opportunity Cost = The value of the project not chosen.

Depreciation
Straight-line Depreciation:
Depr. Expense = (Asset Cost – Scrap Value) / Useful Life
Depr. Rate = 100% / Useful Life
Double Declining Balance Method:
Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
Markus, As usual, very impressive and detailed feedback. I hope you are doing well.
...
1 reply by Markus Kopko
Sep 19, 2016 3:38 AM
Markus Kopko
...
Hi Rami,

thanks for the compliment.
Yes, i am doing well thanks for asking. I hope you to.
Just a bit to much to do the last weeks/months, so i can't contribute here as much as i want to.
But i do have something very nice in the pipeline for projectmanagement. com. I guess it will take part and start of in the beginning of the next year ... we will see ... ;)

Regards,

Markus
avatar
Praveen Malik Independent Consultant| Independent Consultant New Delhi, India
Hi All,

You can download a pdf copy of PMP formulas pocket guide here - http://www.pmbypm.com/download-pmp-formulas-guide-2/

In addition, to understand the formulas, you can look at
1. Earned value management - Click the link to study and understand all the Earned Value Management Formulas (http://www.pmbypm.com/earned-value-management-formulas/)
2. Estimation - Click the link to study and understand all the estimation formulas (http://www.pmbypm.com/three-point-estimate-formulas/)
3. Procurement & Contract types - Click the link to study and understand all the procurement formulas (http://www.pmbypm.com/pmp-formulas-contract-types/)

BR
...
1 reply by Rami Kaibni
Sep 19, 2016 11:20 AM
Rami Kaibni
...
Praveen,

The first link opened but I could not download the guide. Maybe you can guide us through this.

As for the other two links, they opened and the pages showed error.
avatar
Elizabeth Harrin Director| RebelsGuideToPM.com London, England, United Kingdom
I agree that the act of writing them down will help you remember them, so even if you use the lists here, make your own version to help your studies.
...
1 reply by Khaled Al Kolfat
Oct 04, 2016 7:13 AM
Khaled Al Kolfat
...
strongly agree
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Amen, Markus (hehehehehe). Thank you very much for sharing.
...
1 reply by Markus Kopko
Sep 19, 2016 3:39 AM
Markus Kopko
...
You are welcome, Sergio.
< 1 2 3 >