Varun Kumar Gupta Commercial and Scheduling Manager| Design Plus Architects Gurugram, Haryana, India
In the MS Project Software, it is a feature which I am unable to locate
Sort By:
avatar
Anupam India
1. Right click the bar on timeline and select 'Format Bar' from the pop up
2. Select the 'Shape' and 'Color' under Bar Shape
avatar
Stéphane Parent Self Employed / Semi-retired| Leader Maker Prince Edward Island, Canada
Under Project 2013, right click the timeline (Gantt section) and select Bar Style.

Click on Milestone, then go at the bottom of the window and use the Bars and Text tab to change the format.

This will change all milestones in your project.
avatar
Varun Kumar Gupta Commercial and Scheduling Manager| Design Plus Architects Gurugram, Haryana, India
Thank you. I have located it.