Mudassar KhanProgram (Project )Manager| Woodward Canada IncPeterborough, ON, Canada
How to differentiate between Validate Scope from Control Quality Process ?
Are both processes related ?? How Significant is the importance of both in Project Management Practices Saving Changes...
The control quality process is performed to ensure that product is ready to be delivered while validate scope process gets the formal acceptance from the client after delivering the product.
Sergio Luis ConteHelping to create solutions for everyone| Worldwide based OrganizationsBuenos Aires, Argentina
Control quality is performed before Validate scope. Control quality is performed over the deliverables. When you are sure that the deliverables are covering the requirements then you can go to the stakeholders to Validate scope.
...
2 replies by Mudassar Khan
Nov 01, 2016 2:57 AM
Mudassar Khan
...
Thank you :) Your help is appreciated :)
Nov 01, 2016 2:57 AM
Mudassar Khan
...
Thank you Sergio :)
Saving Changes...
AKSHAY JAINPlanning Group Leader| YOKOGAWA, BahrainGwalior, Mp, India
Validate scope is to confirm whether complete scope is covered and quality control is about checking quality of deliverables. Incomplete deliverables can also pass through quality control but does not ensure complete coverage of scope. Saving Changes...
Mudassar KhanProgram (Project )Manager| Woodward Canada IncPeterborough, ON, Canada
Oct 31, 2016 8:44 AM
Replying to Sergio Luis Conte
...
Control quality is performed before Validate scope. Control quality is performed over the deliverables. When you are sure that the deliverables are covering the requirements then you can go to the stakeholders to Validate scope.
Thank you :) Your help is appreciated :) Saving Changes...
Mudassar KhanProgram (Project )Manager| Woodward Canada IncPeterborough, ON, Canada
Oct 31, 2016 8:44 AM
Replying to Sergio Luis Conte
...
Control quality is performed before Validate scope. Control quality is performed over the deliverables. When you are sure that the deliverables are covering the requirements then you can go to the stakeholders to Validate scope.
Thank you Sergio :) Saving Changes...
Pallav RohatgiDirector| Zedroit Global Solution Pvt LtdKolkata, West Bengal, India
Control quality is the process which has to done before Validate Scope .
The project completion and finance is dependent on Validate Scope .
Quality control is performed so that we are verifying Validate Scope. Saving Changes...