Deterioration in skill level

linkedin twitter facebook  
avatar
Chandrashekhar Thatte Pune, Maharashtra, India
With the deterioration in skill level resulting in increasing errors,how can the project tool for time be relied upon when actual data requirement for progress updates is incorrect?Please share your experience ...
Sort By:
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
I am not sure I fully understood your question, can you reiterate please. Thanks !
...
1 reply by Chandrashekhar Thatte
Jan 31, 2017 2:31 AM
Chandrashekhar Thatte
...
The project tool is only as good as the effort used to create it, and
the common errors that occur between progress updates refer to progress percentages decreasing between updates, actual dates changing from ‘it started to hasn’t started’ to a ‘revelation that it started six months ago and we forget to record the actual start or record any progress in the six months.’

Other changes are in duration, both original and remaining, the latter appears to be forgetfulness of the planner when using a physical percentage update method which requires both a percentage and number of days to be entered into Primavera. Any error in the progress update can result in producing an unrealistic forecast completion and or critical path.

So with the deterioration in skill level resulting in increasing errors, the project tool for time can not be relied upon when actual data required for the progress updates is incorrect.

Hope this helps !
avatar
Chandrashekhar Thatte Pune, Maharashtra, India
Jan 30, 2017 12:41 PM
Replying to Rami Kaibni
...
I am not sure I fully understood your question, can you reiterate please. Thanks !
The project tool is only as good as the effort used to create it, and
the common errors that occur between progress updates refer to progress percentages decreasing between updates, actual dates changing from ‘it started to hasn’t started’ to a ‘revelation that it started six months ago and we forget to record the actual start or record any progress in the six months.’

Other changes are in duration, both original and remaining, the latter appears to be forgetfulness of the planner when using a physical percentage update method which requires both a percentage and number of days to be entered into Primavera. Any error in the progress update can result in producing an unrealistic forecast completion and or critical path.

So with the deterioration in skill level resulting in increasing errors, the project tool for time can not be relied upon when actual data required for the progress updates is incorrect.

Hope this helps !