Feb 22, 2017 8:50 AM
Replying to Sungjoon Park
...
This might occur In the case that the contractor might be eligible to have EOT in the specific events but such EOT are not sufficient to complete the project.
For example:
Original completion date : March 10, 2016
Time to extension : 180 days
Revised completion date : September 06, 2016
Substantial completion date : December 05, 2016
Therefore, 90 days of LD might be applicable.
However most of time in my case, LD might be avoidable when the contractor gives up some cost reimbursement from the client due to EOT and additional time to competition can be obtained from the client.