audit

linkedin twitter facebook   Work Breakdown Structures (WBS)  
avatar
Christian Ruff de Conti PM Specialist| EITI Sideco Milan, Lombardia, Italy
Dear all,

after having applied for the PMP exam I have been selected for the audit and I have sent all the required documentation.
Last week I have received the communication from PMP that the process has been closed and considered “Failed No Fault” due to lack of detailed description of how the undersigned directed projects submitted.

Please find below the communication received by PMI:
The project management experience that you have listed on your application does not meet these requirements, because in one or more of your projects there were the following issues:
· Your project management work experience descriptions do not align with the five key process areas of project management (initiating, planning, executing, monitoring and controlling and closing) and we are unable to determine how you lead and directed the projects as detailed in the PMP Exam Content Outline(see link below) and the PMBOK Guide 5th edition section 3.2.
· The deliverables you documented do not indicate how you lead and directed in all five process groups (initiating, planning, executing, monitoring and controlling and closing) across all your projects submitted on the application as detailed in the PMP Exam Content Outline(see link below) and the PMBOK Guide 5th edition section 3.2.
Because your application does not meet the requirements, we are unable to proceed with the audit at this time. Your application and audit have been closed and “Failed No Fault”. If you wish to submit a new application, you may do so at any time. A request for a refund of your application fee will be requested as detailed in the Refund Policy on page 13 of the PMP® Handbook(see link below). Please allow 7-10 days for your refund to be processed; you will receive an email confirmation once the refund is complete.

CONSIDERING THE N.3 FOLLOWING DESCRIPTIONS OF THE EXPERIENCES FILLED IN MY FIRST APPLICATION:

Benetti 50m Yacht ordinary and extraordinary maintenance project manager. The undersigned, commissioned by the shipowner, had to manage all the ordinary and extraordinary maintenance, plan the necessary repairs to be carried out on the Yacht, select the Yard, expedite the daily works in the yard, monitor and control the scope, the schedule, the cost, the procurements and the stakeholder engagement. All the informations had been reported to the during the proceeding of the job to the shipowner and the involved stakeholders.
N.2 44 mt Explorer Motor Yacht design and construction. The undersigned was assigned as project manager for the design and construction of N.2 a.m. vessels. During this experience he was involved in all the phases in which the project had been divided, the five process groups and in all different ten knowledge areas. For the design phase the drawings and structures calculations have been properly submitted on time following the scope with a high quality. The stakholders have been constantly informed during the life of the Project.

Yard UNI ISO 9001 Quality System Manager The undersigned was assigned as quality manager in order to implement the quality system, revise the quality manual, prepare the procedure, instructions and modules for the stakeholders, manage and direct the system, monitor and control it and collect the lesson learned .

PLEASE CONFIRM IF THE FOLLOWING DESCRIPTIONS WILL BE OK TO BE SUBMITTED IN MY SECOND APPLICATION:
Objective: Design of a 44 mt Yacht.
Deliverables: Structural, hydrodynamic and stability calculations. Drawings and 3d model.
As PM I identified the stakeholders and determined their expectations (I), defined the scope, created the WBS and prepared the project schedule plan (P), I directed the engineers and designers acquired during the execution of the calculations, technical drawings and 3d modeling (E). I monitored the quality of the work handling issues and change requests (M) I archive the documents and recorded the lesson learned (C).
Outcome: Drawings and calculations have been delivered on time and finished within scope and budget.

Objective: Construction of a 44 mt Yacht Hull and Superstructures.
Deliverables: Hull and Superstructures of the 44m Yacht.
As PM I identified the stakeholders (I), planned the scope of the project considering time, cost and quality; project plan has been developed including the subsidiary plans (P), directed carpenters and welders during the activities managing issues and change requests (E). I monitored the quality of the work and prepared work performance reports (M) I archived documents and recorded the lesson learned at the end after the final acceptance of deliverables (C).
Outcome: Structures completed within scope, time and budget.

Objective: To create an IT storage system to share projects documents between team members.
Deliverables: IT Storage system.
As PM indicted by the Sponsor, I proceeded with the stakeholder identification (I), I planned the scope of the project, created WBS and project plan (P). I directed the team during the execution of the activities and I implemented the changes (E). I monitored the quality of the work performed, measured project performance and I managed changes (M) and I obtained the acceptance of the IT Storage system from the customer (C).
Outcomes: IT Storage system delivered following all the requirements.
Sort By:
avatar
Markus Kopko AI Enabler for Project & Program Mgmt | Founder PMotion.ai / The PM AI Coach| PMotion.ai Hamburg, Hamburg, Germany
Hi Christian,

you need to assure that your wording is aligned to the tasks and the language used in the PMP content outline document.

This should do the job from my experience (my application was also selected for audit).

In addition you may refer to the following articles:

-------------------------------------
Audit Kit:
? https://goo.gl/q9BGDL
--------------------------------------
When can a PMI Audit happen?
? https://goo.gl/esQdgg
------------------------------------
Three Ways To Fail Your PMP Exam Audit (VIDEO included!):
? https://goo.gl/0tz2LS
------------------------------------
What to Expect from a PMI Audit as Stated in the PMP Credential Handbook (VIDEO inside!)?:
? https://goo.gl/gUIk9P

Help! I’ve Failed The PMP® Audit!
? https://goo.gl/U7gCTl

Hope this helps abit.

Regards,

Markus
avatar
Christian Ruff de Conti PM Specialist| EITI Sideco Milan, Lombardia, Italy
Dear Markus,

Thank you for your reply! Please note that I have red these very useful articles. Anyway considering your experience are you so kind to confirm me if the revised descriptions of my PM experience below attached are now OK, more detailed and aligned with the requested wording?

Objective: Design of a 44 mt Yacht.
Deliverables: Structural, hydrodynamic and stability calculations. Drawings and 3d model.
As PM I identified the stakeholders and determined their expectations (I), defined the scope, created the WBS and prepared the project schedule plan (P), I directed the engineers and designers acquired during the execution of the calculations, technical drawings and 3d modeling (E). I monitored the quality of the work handling issues and change requests (M) I archive the documents and recorded the lesson learned (C).
Outcome: Drawings and calculations have been delivered on time and finished within scope and budget.

Objective: Construction of a 44 mt Yacht Hull and Superstructures.
Deliverables: Hull and Superstructures of the 44m Yacht.
As PM I identified the stakeholders (I), planned the scope of the project considering time, cost and quality; project plan has been developed including the subsidiary plans (P), directed carpenters and welders during the activities managing issues and change requests (E). I monitored the quality of the work and prepared work performance reports (M) I archived documents and recorded the lesson learned at the end after the final acceptance of deliverables (C).
Outcome: Structures completed within scope, time and budget.

Objective: To create an IT storage system to share projects documents between team members.
Deliverables: IT Storage system.
As PM indicted by the Sponsor, I proceeded with the stakeholder identification (I), I planned the scope of the project, created WBS and project plan (P). I directed the team during the execution of the activities and I implemented the changes (E). I monitored the quality of the work performed, measured project performance and I managed changes (M) and I obtained the acceptance of the IT Storage system from the customer (C).
Outcomes: IT Storage system delivered following all the requirements

Looking forward to hearing something from you.

Regards

Christian
...
1 reply by Markus Kopko
Apr 21, 2017 4:07 AM
Markus Kopko
...
Hi Christian,

i have reviewed your descriptions now and from my perspective they look good and plausible.
But that is no guarantee like you may know. I am not a PMI employee and i do also not know what exactly they are looking for.
But if you have considered all the guidelines given before (and it seems that you have do so) this should work out.

I would give it a try. Please let us know how it went.

Regards,

Markus
avatar
Christian Ruff de Conti PM Specialist| EITI Sideco Milan, Lombardia, Italy
Please let me know any feedback!
avatar
Markus Kopko AI Enabler for Project & Program Mgmt | Founder PMotion.ai / The PM AI Coach| PMotion.ai Hamburg, Hamburg, Germany
Apr 20, 2017 6:21 AM
Replying to Christian Ruff de Conti
...
Dear Markus,

Thank you for your reply! Please note that I have red these very useful articles. Anyway considering your experience are you so kind to confirm me if the revised descriptions of my PM experience below attached are now OK, more detailed and aligned with the requested wording?

Objective: Design of a 44 mt Yacht.
Deliverables: Structural, hydrodynamic and stability calculations. Drawings and 3d model.
As PM I identified the stakeholders and determined their expectations (I), defined the scope, created the WBS and prepared the project schedule plan (P), I directed the engineers and designers acquired during the execution of the calculations, technical drawings and 3d modeling (E). I monitored the quality of the work handling issues and change requests (M) I archive the documents and recorded the lesson learned (C).
Outcome: Drawings and calculations have been delivered on time and finished within scope and budget.

Objective: Construction of a 44 mt Yacht Hull and Superstructures.
Deliverables: Hull and Superstructures of the 44m Yacht.
As PM I identified the stakeholders (I), planned the scope of the project considering time, cost and quality; project plan has been developed including the subsidiary plans (P), directed carpenters and welders during the activities managing issues and change requests (E). I monitored the quality of the work and prepared work performance reports (M) I archived documents and recorded the lesson learned at the end after the final acceptance of deliverables (C).
Outcome: Structures completed within scope, time and budget.

Objective: To create an IT storage system to share projects documents between team members.
Deliverables: IT Storage system.
As PM indicted by the Sponsor, I proceeded with the stakeholder identification (I), I planned the scope of the project, created WBS and project plan (P). I directed the team during the execution of the activities and I implemented the changes (E). I monitored the quality of the work performed, measured project performance and I managed changes (M) and I obtained the acceptance of the IT Storage system from the customer (C).
Outcomes: IT Storage system delivered following all the requirements

Looking forward to hearing something from you.

Regards

Christian
Hi Christian,

i have reviewed your descriptions now and from my perspective they look good and plausible.
But that is no guarantee like you may know. I am not a PMI employee and i do also not know what exactly they are looking for.
But if you have considered all the guidelines given before (and it seems that you have do so) this should work out.

I would give it a try. Please let us know how it went.

Regards,

Markus
...
1 reply by Christian Ruff de Conti
May 23, 2017 6:21 AM
Christian Ruff de Conti
...
Dear Markus,

With reference to the communication occurred please note that after having submitted the following revised descriptions of my passed PM experience I finally passed the audit process that I failed the first time!!

TITLE:
Design of a 44 mt Yacht.

DESCRIPTION:
Objective: Design of a 44 mt Yacht. Deliverables: Structural, hydrodynamic and stability calculations.
Drawings and 3d model. As PM I identified the stakeholders and determined their expectations (I), defined the
scope, prepared the project schedule plan (P), I directed the engineers and designers during the execution of the
activities (E). I monitored the quality of the work, handling issues and change requests (M) I archived the
documents and recorded the lesson learned (C). Outcome: Drawings and calculations have been delivered on
time.


TITLE:
44 mt Yacht Hull and Superstructures contruction

DESCRIPTION:
Objective: To Construct 44 mt Yacht Hull and Superstructures. Deliverables: Hull and Superstructures. I
participated in project charter development as PM (I), developed scope, cost, quality, risk, communications and
risk plans (P), directed carpenters and welders during the activities managing issues and change requests,
conducted procurement (E). I monitored the quality of the work (M) I archived documents, recorded the lesson
learned after the final acceptance of deliverables (C). Outcome: Structures completed within scope, time and budget.

TITLE:
Cloud data storage IT system

DESCRIPTION:
Objective: To create a cloud data storage system to share projects documents between team members.
Deliverables: Cloud data storage system.
As PM I proceeded with the stakeholder identification (I), defined the scope of the project, created WBS and
project plan (P). I directed the team during the execution of the (E). I monitored the quality of the work
performed, measured project performance and managed changes (M) the acceptance of the system have been
obtained (C).
Outcomes: IT Storage system delivered following all the requirements.

NOW I CAN SCHEDULE THE EXAM!

Thank you.

Regards

Christian
avatar
Christian Ruff de Conti PM Specialist| EITI Sideco Milan, Lombardia, Italy
Apr 21, 2017 4:07 AM
Replying to Markus Kopko
...
Hi Christian,

i have reviewed your descriptions now and from my perspective they look good and plausible.
But that is no guarantee like you may know. I am not a PMI employee and i do also not know what exactly they are looking for.
But if you have considered all the guidelines given before (and it seems that you have do so) this should work out.

I would give it a try. Please let us know how it went.

Regards,

Markus
Dear Markus,

With reference to the communication occurred please note that after having submitted the following revised descriptions of my passed PM experience I finally passed the audit process that I failed the first time!!

TITLE:
Design of a 44 mt Yacht.

DESCRIPTION:
Objective: Design of a 44 mt Yacht. Deliverables: Structural, hydrodynamic and stability calculations.
Drawings and 3d model. As PM I identified the stakeholders and determined their expectations (I), defined the
scope, prepared the project schedule plan (P), I directed the engineers and designers during the execution of the
activities (E). I monitored the quality of the work, handling issues and change requests (M) I archived the
documents and recorded the lesson learned (C). Outcome: Drawings and calculations have been delivered on
time.


TITLE:
44 mt Yacht Hull and Superstructures contruction

DESCRIPTION:
Objective: To Construct 44 mt Yacht Hull and Superstructures. Deliverables: Hull and Superstructures. I
participated in project charter development as PM (I), developed scope, cost, quality, risk, communications and
risk plans (P), directed carpenters and welders during the activities managing issues and change requests,
conducted procurement (E). I monitored the quality of the work (M) I archived documents, recorded the lesson
learned after the final acceptance of deliverables (C). Outcome: Structures completed within scope, time and budget.

TITLE:
Cloud data storage IT system

DESCRIPTION:
Objective: To create a cloud data storage system to share projects documents between team members.
Deliverables: Cloud data storage system.
As PM I proceeded with the stakeholder identification (I), defined the scope of the project, created WBS and
project plan (P). I directed the team during the execution of the (E). I monitored the quality of the work
performed, measured project performance and managed changes (M) the acceptance of the system have been
obtained (C).
Outcomes: IT Storage system delivered following all the requirements.

NOW I CAN SCHEDULE THE EXAM!

Thank you.

Regards

Christian