A. Individuals and organisations who use the project's product, service or result.
B. Individuals and organisations whose interest may be positively or negatively affected as a result of project execution or successful project completion
C. Individuals and organisations who provide the financial resources for, and oversee the work of the project.
D. Individuals and organisations who could impact, or be impacted by a decision, activity or outcome of the project. Saving Changes...
I would go with D.
B can't explain on those who positively or negatively impact the project. Saving Changes...
Deepesh RammoorthyICT Project Manager ( PMP®AgilePM®Certified ScrumMaster® (CSM®))| Australian Red Cross Blood ServiceTarneit, Vic, Australia
Oops my bad
I agree with Sungjoon . I revisited the Stakeholder Management and D is the correct answer.
page 391 of PMBOK guide Saving Changes...
Drew CraigSr. Agile & Product Coach| VanguardPhiladelphia, Pa, United States
Eh, close, but close only counts in darts, horseshoes, and hand grenades as they say. I didn't have the PMBOK handy. We all make mistakes. : ) Chose D, but talked myself out of it : ( Saving Changes...
Option D
It encompasses all entities affected by all elements of the project.
Each of the other options is missing at least one component. Saving Changes...