Project Stakeholders are defined as:

linkedin twitter facebook   New Practitioners  
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
Re-Tweet from Today's free #PMP question http://www.mosaicprojects.com.au/Training-PMP-Q-Today.html

Project Stakeholders are defined as:

A. Individuals and organisations who use the project's product, service or result.
B. Individuals and organisations whose interest may be positively or negatively affected as a result of project execution or successful project completion
C. Individuals and organisations who provide the financial resources for, and oversee the work of the project.
D. Individuals and organisations who could impact, or be impacted by a decision, activity or outcome of the project.
Sort By:
< 1 2 >
avatar
Drew Craig Sr. Agile & Product Coach| Vanguard Philadelphia, Pa, United States
I'm going with B D .... Final answer.
avatar
Deepesh Rammoorthy ICT Project Manager ( PMP®AgilePM®Certified ScrumMaster® (CSM®))| Australian Red Cross Blood Service Tarneit, Vic, Australia
I am for B as well ....A = Customer , C = Sponsor , D = could be stakeholders but not exactly PMIs definition of a Stakeholder
avatar
Sungjoon Park Coral Springs, Fl, United States
I would go with D.
B can't explain on those who positively or negatively impact the project.
avatar
Deepesh Rammoorthy ICT Project Manager ( PMP®AgilePM®Certified ScrumMaster® (CSM®))| Australian Red Cross Blood Service Tarneit, Vic, Australia
Oops my bad

I agree with Sungjoon . I revisited the Stakeholder Management and D is the correct answer.
page 391 of PMBOK guide
avatar
Drew Craig Sr. Agile & Product Coach| Vanguard Philadelphia, Pa, United States
Eh, close, but close only counts in darts, horseshoes, and hand grenades as they say. I didn't have the PMBOK handy. We all make mistakes. : ) Chose D, but talked myself out of it : (
avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
Now everybody agree on D.

Would have been my choice, everybody and anybody that can be affected or impact the project.
avatar
Mayte Mata Sivera PMO Leader | Speaker | Author Ut, United States
E - A nightmare. (I saw that in a free online test, and I can't stop to laugh when I remember it)
avatar
Aejaz Shaikh PM I| Alyx Technologies India Pvt Ltd Pune, Maharshatra, India
Option - D
avatar
Bala Sripada Hyderabad, Ap, India
Option- B
avatar
Julian Hampson Sr. Advisor, Gas Storage & Transmission Engineering| Enbridge Sarnia, Ontario, Canada
Option D
It encompasses all entities affected by all elements of the project.
Each of the other options is missing at least one component.