Project Stakeholders are defined as:

linkedin twitter facebook   New Practitioners  
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
Re-Tweet from Today's free #PMP question http://www.mosaicprojects.com.au/Training-PMP-Q-Today.html

Project Stakeholders are defined as:

A. Individuals and organisations who use the project's product, service or result.
B. Individuals and organisations whose interest may be positively or negatively affected as a result of project execution or successful project completion
C. Individuals and organisations who provide the financial resources for, and oversee the work of the project.
D. Individuals and organisations who could impact, or be impacted by a decision, activity or outcome of the project.
Sort By:
< 1 2 >
avatar
SUNNY HELWANDE BUSINESS LEAD| ExxonMobil Services Private Limited Dombivli, Maharashtra, India
OPTION D..

anyone who is directly or indirectly impacted by your project are thr project stakeholders.
avatar
Lonnie Pacelli Author & President| ProjectManagementAdvisor.com Bellevue, Wa, United States
The difference between B & D looks almost academic. If the project can help or hurt you in some way then you're a stakeholder.
avatar
Pier Luigi Calabria Project Manager| INFORM Institut für Operations Research und Management GmbH, Aachen, Germany Aachen, Germany
I'd say D, but B is not that wrong either....
avatar
Andre Cassule FEED and Detailed Engineering, Project management| DEAL Luanda, Luanda, Angola
Project Stakeholders are defined as:
Option D: Individuals and organisations who could impact, or be impacted by a decision, activity or outcome of the project.
I also say D. I think the key to understand that B is not the right one are the words "execution" OR "successful completion": stakeholders are not depended on the project phases. B would be correct if stated in this way indeed: "Individuals and organisations whose interest may be positively or negatively affected by the project"
avatar
Sonali Malu Maharashtra, India
B and D are very close. When I referred PMBOK again, found D is the most accurate.
avatar
Sea Wai Cheng PM Specialist| GLD Hong Kong, Hong Kong
All of them
avatar
Fazal Hussain Aasar Community Manager| TaskQue Pakistan
Option D is the right option but the answer can be expanded further.
< 1 2 >

Please login or join to reply

Content ID:
ADVERTISEMENTS

"It is impossible to travel faster than the speed of light, and certainly not desirable, as one's hat keeps blowing off."

- Woody Allen

ADVERTISEMENT

Sponsors