uestion 11 - Qid 10046, Cost Management, Monitoring & Controlling, Control Costs
You are managing a project to install upgraded communications equipment for an emergency medical dispatch department within the local fire department and your project budget is $20,000. You have spent $17,000 so far and the project is 75% complete. A new project budget of $25,000 has been approved. What should your To Complete Cost Performance (TCPI) be if you want to complete your project within the new approved budget?
1.667
0.882
0.625
0.521

I can not solve above question? any help?
Sort By:
avatar
Eric Simms Senior Program Manager Baltimore, Maryland, United States
The answer is .882. The key is to calculate the Earned Value based on the previous budget of $20,000, not the new budget of $25,000. This makes sense because the work was already completed under the old budget. Here are my calculations:

Budget at Completion (BAC) = 25,000
Actual Cost (AC) = 17,000
Earned Value (EV) = 75% of 20,000 = 15,000
Cost Performance Index (CPI) = EV / AC
= 15,000/17,000
= .8823529

Estimate at Completion (EAC) = BAC/CPI
25,000/.8823529 = 28,333.23

TCPI = (BAC – EV)/(EAC – AC)
= (25,000-15,000)/(28,333.23-17,000)
= 10,000/11,333.23
= .882
...
1 reply by Suhail Iqbal
May 06, 2017 3:38 PM
Suhail Iqbal
...
I agree with you but if you use BAC as $20000, and calculate CPI also based on that, the answer will still be the same.
avatar
MANSOUR THABET ALQUBATY System Controller| Teleyemen Sana'A, N/A, Yemen
Hello,

My answer is the first choice , however my question why he provided a second BAC ($25000)?

Thanks
...
1 reply by Suhail Iqbal
May 06, 2017 3:39 PM
Suhail Iqbal
...
no way
avatar
Suhail Iqbal Suhail Iqbal PMIATP CIPM FAAPM MPM MQM CLC CPRM SCT AEC SDC SMC SPOC PRINCE2 MCT| PM Training School Rawalpindi, Punjab, Pakistan
May 06, 2017 1:08 PM
Replying to Eric Simms
...
The answer is .882. The key is to calculate the Earned Value based on the previous budget of $20,000, not the new budget of $25,000. This makes sense because the work was already completed under the old budget. Here are my calculations:

Budget at Completion (BAC) = 25,000
Actual Cost (AC) = 17,000
Earned Value (EV) = 75% of 20,000 = 15,000
Cost Performance Index (CPI) = EV / AC
= 15,000/17,000
= .8823529

Estimate at Completion (EAC) = BAC/CPI
25,000/.8823529 = 28,333.23

TCPI = (BAC – EV)/(EAC – AC)
= (25,000-15,000)/(28,333.23-17,000)
= 10,000/11,333.23
= .882
I agree with you but if you use BAC as $20000, and calculate CPI also based on that, the answer will still be the same.
avatar
Suhail Iqbal Suhail Iqbal PMIATP CIPM FAAPM MPM MQM CLC CPRM SCT AEC SDC SMC SPOC PRINCE2 MCT| PM Training School Rawalpindi, Punjab, Pakistan
May 06, 2017 1:44 PM
Replying to MANSOUR THABET ALQUBATY
...
Hello,

My answer is the first choice , however my question why he provided a second BAC ($25000)?

Thanks
no way
avatar
Sungjoon Park Coral Springs, Fl, United States
0.625

Work Remaining : 5000 (20000-15000)
Budget Remaining : 8000(25000-17000)

TCPI= Work remaining/Budget remaining = 5/8=0.625
avatar
MANSOUR THABET ALQUBATY System Controller| Teleyemen Sana'A, N/A, Yemen
Hello,

I got the answer only now and I think the best answer is 0.625

Thanks mr. Sungjoon Park (you get it).
TCPI= (BAC-EV)/(BAC- AC) -----------------(BAC-EV)= work left to do ....is (5000)
(BAC- AC) = left Money .... is (8000)

Every day we still learning new things!!!
Thanks for sharing from all participants.
BR,
Mansour
avatar
Liana Underwood National Capital Region, Va, United States
Math in the house, look at you all go!
avatar
ahmed elzeny senior technical office engineer| elmadar eloula for consulting riyadah, Saudi Arabia
.882
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
My recommendation, if you are preparing for the certification exam then use PMI´s AI tool because it is supposed it has the PMI knowledge in their base (something I do not have opportunity to validate because I asked lot of times but I did not received answers yet)

Please login or join to reply

Content ID:
ADVERTISEMENTS
ADVERTISEMENT

Sponsors