Can someone explain what is the meaning of Approved Change Requests?

linkedin twitter facebook   Work Breakdown Structures (WBS)  
avatar
Tam Nguyen Annandale, Va, United States
Can someone explain what is the meaning of Approved Change Requests?
Sort By:
avatar
Raymond Colony Project Manager, eBusiness| The HON Company Iowa City, Ia, United States
In organizations with well defined customer requirements, a Change Request is a formal request from the customer to change a deliverable or otherwise somehow change the scope of a set of requirements. Once submitted by the customer, it is reviewed by the project and the level of effort (and thus the cost difference if any) is determined and communicated back to the customer. Once the customer accepts to take on the financial repercussions and and delivery impact it may carry, it is an Approved Change Request and once codified properly within the SOW and the companies legal and contractual practices, can be scheduled for inclusion in the project.
...
1 reply by Tam Nguyen
Jun 14, 2017 4:22 AM
Tam Nguyen
...
much appreciate.
avatar
Deepesh Rammoorthy ICT Project Manager ( PMP®AgilePM®Certified ScrumMaster® (CSM®))| Australian Red Cross Blood Service Tarneit, Vic, Australia
From PMP point of view an Approved Change Request is a Change Request that has undergone Integrated Change Control Process.
This also means, the change has been analysed for it's impacts, Risks, Scope and the Change Board (including sponsor/customer) is happy to accept the changed scope/time/cost/Quality/HR/Customer Satisfaction implications.

This eventually means that the Project Manager now needs to update the performance Measurement Baselines (Cost/time/scope) to reflect the approved change.

This would mean the Project Manager would need to change every single Project Management document that is impacted by the approved change - HR Management Plan if resources are added/removed , Scope Management Plan and all relevant scope items - WBS, WBS-dictionary as scope is changed, Cost Management Plan , if Budget is changed, Schedule Management Plan and all relevant schedule documentation .

This will happen as outputs of DIRECT AND MANAGE Project work process, an execution process.
...
1 reply by Tam Nguyen
Jun 14, 2017 4:21 AM
Tam Nguyen
...
thank for your commitment. It is very useful
avatar
Tam Nguyen Annandale, Va, United States
Jun 14, 2017 1:00 AM
Replying to Deepesh Rammoorthy
...
From PMP point of view an Approved Change Request is a Change Request that has undergone Integrated Change Control Process.
This also means, the change has been analysed for it's impacts, Risks, Scope and the Change Board (including sponsor/customer) is happy to accept the changed scope/time/cost/Quality/HR/Customer Satisfaction implications.

This eventually means that the Project Manager now needs to update the performance Measurement Baselines (Cost/time/scope) to reflect the approved change.

This would mean the Project Manager would need to change every single Project Management document that is impacted by the approved change - HR Management Plan if resources are added/removed , Scope Management Plan and all relevant scope items - WBS, WBS-dictionary as scope is changed, Cost Management Plan , if Budget is changed, Schedule Management Plan and all relevant schedule documentation .

This will happen as outputs of DIRECT AND MANAGE Project work process, an execution process.
thank for your commitment. It is very useful
avatar
Tam Nguyen Annandale, Va, United States
Jun 13, 2017 8:22 PM
Replying to Raymond Colony
...
In organizations with well defined customer requirements, a Change Request is a formal request from the customer to change a deliverable or otherwise somehow change the scope of a set of requirements. Once submitted by the customer, it is reviewed by the project and the level of effort (and thus the cost difference if any) is determined and communicated back to the customer. Once the customer accepts to take on the financial repercussions and and delivery impact it may carry, it is an Approved Change Request and once codified properly within the SOW and the companies legal and contractual practices, can be scheduled for inclusion in the project.
much appreciate.
avatar
Seema Sonkiya Head Business Analysis Practices, PMI-PBA trainer| iZenBridge Consultancy Private Limited Jaipur, Rajasthan, India
Just to add I advise to watch following video: https://www.youtube.com/watch?v=O1rt_6j2J08