Can someone explain why Approved Change Request is input of Direct and Manage Project Work?

linkedin twitter facebook  
avatar
Tam Nguyen Annandale, Va, United States
Can someone explain why Approved Change Request is the input of Direct and Manage Project Work?
Sort By:
avatar
Seema Sonkiya Head Business Analysis Practices, PMI-PBA trainer| iZenBridge Consultancy Private Limited Jaipur, Rajasthan, India
Direct and Manage Project Work is the process to direct and managing the project work. This process produces deliverables which goes to the customer after validated and acceptance of these deliverables.
Deliverables are also produced from the specification of approved changes.
...
2 replies by Tam Nguyen
Jun 16, 2017 12:07 PM
Tam Nguyen
...
Can you give me an example? I do not clear. Thank you so much
Jun 16, 2017 12:09 PM
Tam Nguyen
...
The approved Change Request is an input of Direct and Manage Project work but the output of that is Change request?
avatar
Sonali Malu Maharashtra, India
In simple terms, Direct and Manage Project Work talks about execution of work.
And Approved Change Request is the approved work to be performed.
Hence, the work to be performed becomes an input to the execution process.
...
2 replies by Tam Nguyen
Jun 16, 2017 12:13 PM
Tam Nguyen
...
thank you so much.
Jun 16, 2017 12:13 PM
Tam Nguyen
...
Now I got it
avatar
Kanna Pod project manager| ABc Bremen, Bremen, Germany
Approved change requests contains some extra efforts / new added scope which is agreed / approved and in Direct and Manage Project Work , where in the work happens and the Project Team converts into desired delivarables.
...
1 reply by Tam Nguyen
Jun 16, 2017 12:14 PM
Tam Nguyen
...
thank you so much
avatar
Cheikh FAYE Microsoft Dynamics 365 Business Expert, CEO and owner| Eurêka Technologies Dakar, Senegal
Effectively, the approved change request may be a corrective action, a preventive action or a defect repair. Approved change requests are scheduled and implemented by the project team and can impact any area of the project or project management plan. The approved change request can also modify the policies, project management, procedures, costs or budget or revise the schedule.
...
1 reply by Tam Nguyen
Jun 16, 2017 12:14 PM
Tam Nguyen
...
Very thanks
avatar
Tam Nguyen Annandale, Va, United States
Jun 14, 2017 5:59 AM
Replying to Seema Sonkiya
...
Direct and Manage Project Work is the process to direct and managing the project work. This process produces deliverables which goes to the customer after validated and acceptance of these deliverables.
Deliverables are also produced from the specification of approved changes.
Can you give me an example? I do not clear. Thank you so much
avatar
Tam Nguyen Annandale, Va, United States
Jun 14, 2017 5:59 AM
Replying to Seema Sonkiya
...
Direct and Manage Project Work is the process to direct and managing the project work. This process produces deliverables which goes to the customer after validated and acceptance of these deliverables.
Deliverables are also produced from the specification of approved changes.
The approved Change Request is an input of Direct and Manage Project work but the output of that is Change request?
avatar
Tam Nguyen Annandale, Va, United States
Jun 14, 2017 7:23 AM
Replying to Sonali Malu
...
In simple terms, Direct and Manage Project Work talks about execution of work.
And Approved Change Request is the approved work to be performed.
Hence, the work to be performed becomes an input to the execution process.
thank you so much.
avatar
Tam Nguyen Annandale, Va, United States
Jun 14, 2017 7:23 AM
Replying to Sonali Malu
...
In simple terms, Direct and Manage Project Work talks about execution of work.
And Approved Change Request is the approved work to be performed.
Hence, the work to be performed becomes an input to the execution process.
Now I got it
avatar
Tam Nguyen Annandale, Va, United States
Jun 14, 2017 9:06 AM
Replying to Kanna Pod
...
Approved change requests contains some extra efforts / new added scope which is agreed / approved and in Direct and Manage Project Work , where in the work happens and the Project Team converts into desired delivarables.
thank you so much
avatar
Tam Nguyen Annandale, Va, United States
Jun 14, 2017 10:14 AM
Replying to Cheikh FAYE
...
Effectively, the approved change request may be a corrective action, a preventive action or a defect repair. Approved change requests are scheduled and implemented by the project team and can impact any area of the project or project management plan. The approved change request can also modify the policies, project management, procedures, costs or budget or revise the schedule.
Very thanks

Please login or join to reply