Why does Requirement Management Plan that describes how requirement will be analyzed happen before Collect Requirement? In my opinion, we should Collect Requirement before Requirement Management Plan

linkedin twitter facebook  
avatar
Tam Nguyen Annandale, Va, United States
Why does Requirement Management Plan that describes how requirement will be analyzed happen before Collect Requirement? In my opinion, we should Collect Requirement before Requirement Management Plan.
avatar
Ed Tsyitee Jr Consultant | Consultant Tucson, Az, United States
If you don't know how you are going to analyze it, why collect it in the first place? It may seem out of step, but really it speeds up the process. Also, requirements can change according to stakeholder and sponsors input and influence, which can take longer to finalize.

Please login or join to reply

Content ID:
ADVERTISEMENTS

"I never resist temptation, because I have found that things that are bad for me do not tempt me."

- George Bernard Shaw

ADVERTISEMENT

Sponsors