You are taking a project during project planning and discover that six individuals have signed the project charter. Which is the following should MOST concern you ? 1. Who will be the member of the
You are taking a project during project planning and discover that six individuals have signed the project charter. Which is the following should MOST concern you ?
1. Who will be the member of the Change Control Board
2. Spending more time on more configuration management
3. Getting a single sponsor (I assume this would be the right answer)
4. Determine the reporting structure Saving Changes...
Deepesh RammoorthyICT Project Manager ( PMP®AgilePM®Certified ScrumMaster® (CSM®))| Australian Red Cross Blood ServiceTarneit, Vic, Australia
The answer is 2 . Spending more time on Configuration Management . More sponsors means varied requirements, varied needs, varied expectations. It means balancing the needs of all the sponsors to achieve the project objectives. It means , not to miss any Stakeholder or Any requirement It means more communication . It means more configuration management. Configuration Management is about maintaining baseline documentations and documentation updates and records management to reflect the current state at all times. It also means you should expect more risks and more change requests in the project which are going to affect your project constraints. Saving Changes...