Can someone help me to solve this problem? Suppose I want to build a house by using Rolling Wave Planning

linkedin twitter facebook   Work Breakdown Structures (WBS)  
avatar
Tam Nguyen Annandale, Va, United States
Can someone help me to solve this problem? Suppose I want to build a house by using Rolling Wave Planning
Sort By:
avatar
Mike Dewing Senior Project Manager / Program Manager| MLD Holdings Ltd. Surrey, British Columbia, Canada
You have to be realistic.

You need the plans in place to pour the foundation. That means there will be walls that will go on top of the foundation and the roof has to fit on those walls. Some things will be very expansive to 'tweak' in subsequent phases.

Having said that there are things that can be planned out a little later on. For example... color schemes, landscaping, furniture, etc can all be pushed into phase 2,3,4 depending.

Unlikely your going to decide to buy a brown leather love seat that will go in the south east corner of the living room and be facing that 56" HP Smart TV when your looking for some land to buy.

:-)
avatar
Deepesh Rammoorthy ICT Project Manager ( PMP®AgilePM®Certified ScrumMaster® (CSM®))| Australian Red Cross Blood Service Tarneit, Vic, Australia
Mind You , Rolling wave planning is not used in construction industry in practice. Especially if you are building a house with a construction company.
You have color schemes and landscaping locked in with the builder , even before the builder lays the first foundation slab.

You are better of thinking about a software development project in terms of rolling wave planning and your schedule can have the high level WBS elements and you can elaborate on the detailed activities as more information becomes available.
...
1 reply by Tam Nguyen
Jun 29, 2017 10:37 PM
Tam Nguyen
...
Awesome, I always think about the construction industry. Thus, I can not know how to use this method. thank you
avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
If you where to build a house?
You can have a general planning first with search for location, purchase the land, get and architect to design the external frame, foundation work, external envelop, more design for interior and interior finishing.

when one step is done you start to put more detail in the next phase.

At some point you might have the general building (house) build but many room not define and du construction one by one has you define what you need.
...
1 reply by Tam Nguyen
Jun 29, 2017 10:39 PM
Tam Nguyen
...
Thank for answering me. How is about missing some activities we did when we are in current activities
avatar
Krishna Pakki Project Services Manager| Rio Tinto Gilbert, Az, United States
agreeing to above comments. Think this way, you have a level 1 time line for completing your house.... then, you have a level 3/4 detailed activities on what to do in the next 3 months.... as you keep going forward to keep developing the next detail
...
2 replies by Tam Nguyen
Jun 29, 2017 10:41 PM
Tam Nguyen
...
Thank for answering me. But How do we fixed some failure that we did when we are in current state
Jun 29, 2017 10:41 PM
Tam Nguyen
...
For instance, we are in level 3 but in level 1 we missed some activities
avatar
Paras Dua Ghaziabad, Uttar Pradesh, India
I got my house constructed / renovated three times so certainly agree that rolling wave in construction project will always overshoot the budget.

The best way to go about doing any project is to freeze as much as scope you can in the beginning so that there is less deviation later on. Colors of the walls or the type of television or the sofa upholstery can be decided later on as they will fall under the bracket of -5% - +10% of cost variance in the project.

As a project manager it is important for you to understand the difference between a permissible change like type of Chimney in the Kitchen in a project which will not move its foundation and a real showstopper like placement of stairs blocking the complete view towards the sea.
...
1 reply by Tam Nguyen
Jun 29, 2017 10:42 PM
Tam Nguyen
...
much thankful your commitment.
avatar
Tam Nguyen Annandale, Va, United States
Jun 27, 2017 8:36 PM
Replying to Deepesh Rammoorthy
...
Mind You , Rolling wave planning is not used in construction industry in practice. Especially if you are building a house with a construction company.
You have color schemes and landscaping locked in with the builder , even before the builder lays the first foundation slab.

You are better of thinking about a software development project in terms of rolling wave planning and your schedule can have the high level WBS elements and you can elaborate on the detailed activities as more information becomes available.
Awesome, I always think about the construction industry. Thus, I can not know how to use this method. thank you
avatar
Tam Nguyen Annandale, Va, United States
Jun 27, 2017 10:40 PM
Replying to Vincent Guerard
...
If you where to build a house?
You can have a general planning first with search for location, purchase the land, get and architect to design the external frame, foundation work, external envelop, more design for interior and interior finishing.

when one step is done you start to put more detail in the next phase.

At some point you might have the general building (house) build but many room not define and du construction one by one has you define what you need.
Thank for answering me. How is about missing some activities we did when we are in current activities
avatar
Tam Nguyen Annandale, Va, United States
Jun 27, 2017 11:32 PM
Replying to Krishna Pakki
...
agreeing to above comments. Think this way, you have a level 1 time line for completing your house.... then, you have a level 3/4 detailed activities on what to do in the next 3 months.... as you keep going forward to keep developing the next detail
Thank for answering me. But How do we fixed some failure that we did when we are in current state
avatar
Tam Nguyen Annandale, Va, United States
Jun 27, 2017 11:32 PM
Replying to Krishna Pakki
...
agreeing to above comments. Think this way, you have a level 1 time line for completing your house.... then, you have a level 3/4 detailed activities on what to do in the next 3 months.... as you keep going forward to keep developing the next detail
For instance, we are in level 3 but in level 1 we missed some activities
avatar
Tam Nguyen Annandale, Va, United States
Jun 28, 2017 12:29 AM
Replying to Paras Dua
...
I got my house constructed / renovated three times so certainly agree that rolling wave in construction project will always overshoot the budget.

The best way to go about doing any project is to freeze as much as scope you can in the beginning so that there is less deviation later on. Colors of the walls or the type of television or the sofa upholstery can be decided later on as they will fall under the bracket of -5% - +10% of cost variance in the project.

As a project manager it is important for you to understand the difference between a permissible change like type of Chimney in the Kitchen in a project which will not move its foundation and a real showstopper like placement of stairs blocking the complete view towards the sea.
much thankful your commitment.

Please login or join to reply