linkedin twitter facebook   Estimating  
avatar
Tam Nguyen Annandale, Va, United States
How to calculate Feeding Buffer?
Sort By:
avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
I found this that explain in simple term
The difference between project buffer vs feeding buffer vs resource buffer
http://innovativeprojectguide.com/project-...rce-buffer.html

Project Buffer
It is a reserve inserted at end of the project. Any delay in the Longest Path will consume some or all of the buffer, and the completion date will not change.

Feeding Buffers:
It is a buffer that is inserted before the first activity on the Critical Chain. This is to ensure that any tasks feeding into the Critical Chain may not delay the Critical Chain. When a delay does occur in the feeding activities, the feeding buffer is consumed so that Critical Chain is not affected.

Resource Buffers:
These are dummy activities with critical resource assignment, added at one or more places on the Critical Chain with so as to ensure that the resource is available and committed to be utilized if needed.
...
1 reply by Tam Nguyen
Jul 02, 2017 11:06 PM
Tam Nguyen
...
I have read another research that said Feeding Buffer placed at the end of non-critical path where it goes into Critical Chain. Is it corrective Mr. Vincent?
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
A further note on Vincent's explanation: the duration of the project buffer is sometimes 50% of the contingency that's removed from each task estimate.
...
1 reply by Tam Nguyen
Jul 02, 2017 11:06 PM
Tam Nguyen
...
Thank for your help.
avatar
Tam Nguyen Annandale, Va, United States
Jul 02, 2017 8:34 PM
Replying to Vincent Guerard
...
I found this that explain in simple term
The difference between project buffer vs feeding buffer vs resource buffer
http://innovativeprojectguide.com/project-...rce-buffer.html

Project Buffer
It is a reserve inserted at end of the project. Any delay in the Longest Path will consume some or all of the buffer, and the completion date will not change.

Feeding Buffers:
It is a buffer that is inserted before the first activity on the Critical Chain. This is to ensure that any tasks feeding into the Critical Chain may not delay the Critical Chain. When a delay does occur in the feeding activities, the feeding buffer is consumed so that Critical Chain is not affected.

Resource Buffers:
These are dummy activities with critical resource assignment, added at one or more places on the Critical Chain with so as to ensure that the resource is available and committed to be utilized if needed.
I have read another research that said Feeding Buffer placed at the end of non-critical path where it goes into Critical Chain. Is it corrective Mr. Vincent?
avatar
Tam Nguyen Annandale, Va, United States
Jul 02, 2017 8:53 PM
Replying to Sante Delle-Vergini, PhD
...
A further note on Vincent's explanation: the duration of the project buffer is sometimes 50% of the contingency that's removed from each task estimate.
Thank for your help.