When do we should use Resource Smoothing and When we should use Resource Leveling?

linkedin twitter facebook   Estimating  
avatar
Tam Nguyen Annandale, Va, United States
When do we should use Resource Smoothing and When we should use Resource Leveling?
Sort By:
< 1 2 >
avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
I suggest to look at
https://www.izenbridge.com/blog/underlinin...urce-smoothing/
...
1 reply by Tam Nguyen
Jul 02, 2017 11:08 PM
Tam Nguyen
...
Again thank you Mr. Vincent
avatar
Mahalmadane Touré Engineer| National Headquarters of Geology and Mines of Mali (Bamako) Mali
We use the resource leveling when we have to deal with project resources' constraint without changing the project schedule baseline. In other words the original estimated schedule will not change. But with resource leveling the project schedule baseline may change.
...
1 reply by Tam Nguyen
Jul 02, 2017 11:10 PM
Tam Nguyen
...
Yes, I agree with your answer. Thank you so much
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Yes the key issue that are addressed by these methods is resource constraints.
...
1 reply by Tam Nguyen
Jul 02, 2017 11:09 PM
Tam Nguyen
...
Can you help me to explain more about that. Thank you so much
avatar
Tam Nguyen Annandale, Va, United States
Jul 02, 2017 6:39 PM
Replying to Vincent Guerard
Again thank you Mr. Vincent
avatar
Tam Nguyen Annandale, Va, United States
Jul 02, 2017 8:45 PM
Replying to Sante Delle-Vergini, PhD
...
Yes the key issue that are addressed by these methods is resource constraints.
Can you help me to explain more about that. Thank you so much
avatar
Tam Nguyen Annandale, Va, United States
Jul 02, 2017 6:56 PM
Replying to Mahalmadane Touré
...
We use the resource leveling when we have to deal with project resources' constraint without changing the project schedule baseline. In other words the original estimated schedule will not change. But with resource leveling the project schedule baseline may change.
Yes, I agree with your answer. Thank you so much
avatar
Atul Gaur Pune, Maharashtra, India
Resource Leveling: It is a resource optimization technique in which the start and finish dates are adjusted to keep the resource utilization at optimum level. It is used when there is a resource constraint, when critically required resources are available only during a particular time period, or i limited quantity or deputed elsewhere. Resource leveling usually results in increase in project duration.
Resource Smoothing: The activities are adjusted such that the resources are not allowed to increase a predefined limit. The dates are allowed to change within the free and total float. Hence the critical path does not change. Resource optimization is not achieved with resource smoothing.
avatar
Deepa Kalangi Manager, Program Management, Author, Trainer| CVS Health Charlotte, NC, United States
Atul nailed it down. I have used both depending on the projects and company's goals.
avatar
Seema Sonkiya Head Business Analysis Practices, PMI-PBA trainer| iZenBridge Consultancy Private Limited Jaipur, Rajasthan, India
Here is the short and crisp video on Resource Leveling and Resource Smoothing

https://www.youtube.com/watch?v=2cN0xcjZEI4
...
1 reply by Tam Nguyen
Jul 04, 2017 5:49 PM
Tam Nguyen
...
Thank you, Seema. I love Izenbridge
avatar
Tam Nguyen Annandale, Va, United States
Jul 04, 2017 2:22 AM
Replying to Seema Sonkiya
...
Here is the short and crisp video on Resource Leveling and Resource Smoothing

https://www.youtube.com/watch?v=2cN0xcjZEI4
Thank you, Seema. I love Izenbridge
...
1 reply by Seema Sonkiya
Jul 05, 2017 2:46 AM
Seema Sonkiya
...
You are welcome!!
< 1 2 >