Schedule Refinement and Rebaseline Definitions

linkedin twitter facebook  
avatar
Dave Cahail Seattle, Wa, United States
We are trying to implement a scheduling guideline policy and need a definition of 'Refinement' and 'Rebaseline'. We could create one ourselves but would like to find something that is already in use or an industry standard. We know the criteria that will justify each definition so that should not be part of the definition.
avatar
Mark Price Perry Business Driven PMO Evangelist| BOT International Orlando, Fl, United States
Dear Dave, in our scheduling policy we use the following definitions: Refinement - an approved change in the project scope, schedule, or budget. The baseline is not changed and project performance is measured against the unchanged original baseline. Rebaseline - an approved change in the project scope, schedule, or budget. The baseline is changed and project performance is measured against the new baseline. We, too, have criteria for the above definitions. Hope this helps. -- Mark Perry, VP of Customer Care, BOT International

Please login or join to reply

Content ID:
ADVERTISEMENTS

"Thousands of candles can be lighted from a single candle, and the life of the candle will not be shortened. Happiness never decreases by being shared."

- Buddha

ADVERTISEMENT

Sponsors