Is it possible to realize kick-off meeting before starting the project without Project core team or without all parties involved in the project?

linkedin twitter facebook  
avatar
Andre Cassule FEED and Detailed Engineering, Project management| DEAL Luanda, Luanda, Angola
Is it possible to realize kick-off meeting before starting the project without Project core team or without all parties involved in the project?
I refer in the execution phase of a project.
Sort By:
avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
Who do you plan to have?
if not project core team
avatar
Mayte Mata Sivera PMO Leader | Speaker | Author Ut, United States
Kickoff without key stakeholders o core team members...I have the same question than Vincent...then who? and what is the proposal of the meeting?
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
As any other activity project kickoff must have a plan associated to it. The plan will answer what/when/who/how/cost defined and the why the plan is created. With all these into account your question is answered.
avatar
Deepa Kalangi Manager, Program Management, Author, Trainer| CVS Health Charlotte, NC, United States
Both Core Team and High level scope and Plan are required to conduct a kick off. Otherwise, the purpose is defeated.
avatar
Sonali Malu Maharashtra, India
Important stakeholders and core team members are very important for kick-off meeting at any stage.
avatar
Eduard Hernandez
Community Champion
Product Operations Program Manager Barcelona, Cataluña, Spain
It is not a good practice to hold a kick-off meeting before having defined the core team members.
avatar
Liming Wu PM Consultant| Capgemini Hangzhou, Zhejiang, China, Mainland
It's really rare that a kick-off meeting is run without the core team. It has something to do with what objective the meeting needs to achieve? If it's just for sponsor to indicate a project is started, then that's ok. The core team can be recruited later and informed of the project information.
avatar
KUMARAGURU M.R. PM| Robert Bosch Engineering and Business Solutions Lt Madurai, Tamil Nadu, India
Its good to do "Kick-off" after freezing the Project plan ( scope, schedule, stakeholders,communication, configuration plan..etc).

But if the project what you are talking abt is
# small
# team or department are co-located.
#organisation has very much experienced in handling similar projects
#lot of re-usability is already in place.
#Project success rate is higher
#Customer not hard on deadlines.
then you can kick-off once Project charter is ready ( with sponsor, sales and Line manager)
avatar
RAJESH K L Project Manager, PMP| Bharat Electronics, Bengaluru, India Bengaluru, Karnataka, India
In my view, without Project core team or without all parties involved in the project, it cannot be termed Kick off meeting. I agree with Kumaraguru