MS Project 2003 questions...can anyone help???

linkedin twitter facebook  
avatar
Riaz Patel Sydney, Australia
Hello. Not been working with project for long hence the basic nature of the questions...

1. having already setup a project i'm now in a position where i have to change the working time for all resources on the project. I know how to do this but know that as a consequence of the change all durations for tasks are going to change....how do i set project to keep the duration fixed and to just change the effort required for each item?
2. Simple formatting issue: I'm having problems working out how to 'wrap text' within any particular column....anyone have the answer?

Any advice would be very much appreciated!