All I am giving a class hand out to a group of PM's and I am needing the answer to this question. greatly appreciate the answer and how you solved it.
A project manager has been asked by the client to meet the promise date of the project. The PM analyzes the schedule before promising a date to the client. The PM uses the program evaluation and reviwe technique to evaluate the project schedule. She decides that based on the results of the PERT calculation she can promise a delivery date of June 30. The expected value of the project completion date is May 30. If the project manager is willing to accept a 5% probability that the project will be delivered later than June 30, what is the standard deviation of the durations of the activities on the critical path, Assume a five day work week.
We are all stumped here on how to calculate. Thanks in advance who all respond :) Saving Changes...