A graphic display of project team members and their reporting relationships is known as:

linkedin twitter facebook  
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
A graphic display of project team members and their reporting relationships is known as a:

A. Resource calendar.
B. Project organization chart.
C. Resource breakdown structure (RBS).
D. Responsibility assignment matrix (RAM).
Sort By:
< 1 2 >
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
Tricky...
avatar
Deepesh Rammoorthy ICT Project Manager ( PMP®AgilePM®Certified ScrumMaster® (CSM®))| Australian Red Cross Blood Service Tarneit, Vic, Australia
Project Organization chart .....is the correct answer.

A resource calendar indicates when Resources are available to do the work ,
A Resource Break down structure includes other resources like equipment , documentation apart from Human Resources,
A Responsibility Assignment Matrix tells who is Responsible, Accountable, Informed and Consulted for activities......
avatar
Najam Mumtaz Retired Lahore, Punjab, Pakistan
I agree with Deepesh

A project organization chart is a graphic display of project team members and their reporting relationships
avatar
Peter Ambrosy Weinheim, Germany
the words "graphic display" and "reporting relationship" point clearly to B.
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Yeah, it's B - this is one of the questions from the PM Challenge exam item pool...

Kiron
avatar
Stéphane Parent Self Employed / Semi-retired| Leader Maker Prince Edward Island, Canada
What is B, George? :)
...
1 reply by George Lewis
Sep 13, 2017 3:03 PM
George Lewis
...
Stephane, you're correct!!!
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
Sep 13, 2017 2:23 PM
Replying to Stéphane Parent
...
What is B, George? :)
Stephane, you're correct!!!
...
1 reply by Stéphane Parent
Sep 13, 2017 3:12 PM
Stéphane Parent
...
I'll take pot pourri for a $1000, George.
avatar
Stéphane Parent Self Employed / Semi-retired| Leader Maker Prince Edward Island, Canada
Sep 13, 2017 3:03 PM
Replying to George Lewis
...
Stephane, you're correct!!!
I'll take pot pourri for a $1000, George.
avatar
Sergio Barrak Project Manager| RiskAIXpert Vantaa, Finland
Agree with Deepesh, B!
avatar
Sajjad Ali Engineer| TDR Pakistan
project organization chart