Elizabeth HarrinDirector| RebelsGuideToPM.comLondon, England, United Kingdom
We don't use EVM for our IT or business projects. I think it's more suited to environments with less ambiguity of outcome and greater project management maturity.
...
1 reply by Vincent Guerard
Nov 07, 2017 5:22 PM
Vincent Guerard
...
Most of those I see using EVM are in large construction projects.
Kiron made a good point related to agile delivery practices. Of course, you can still translate into PV and EV, however with a given stable team with a quite constant velocity and standard cost rates, the EVM metrics information for such cases is limited.
I have been doing IT project management for over twenty years, Vincent. We definitely use the EVM indices (CPI and SVI) to see if we are off track. EAC is not used very much.
That is also my experience in most project the basic is use. Saving Changes...
We don't use EVM for our IT or business projects. I think it's more suited to environments with less ambiguity of outcome and greater project management maturity.
Most of those I see using EVM are in large construction projects. Saving Changes...
Kiron made a good point related to agile delivery practices. Of course, you can still translate into PV and EV, however with a given stable team with a quite constant velocity and standard cost rates, the EVM metrics information for such cases is limited.