EVM usage in you projects

linkedin twitter facebook   Cost Management   Earned Value Management   Estimating   Risk Management  
avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
In your project is EVM really use? Fully? a limited implementation?

You feel it improve project management compare to project that didn't use EVM
What industry are you from?

Also there is a poll
https://www.projectmanagement.com/polls/41...your-projects-?
Sort By:
< 1 2 3 4 >
avatar
Krishna Pakki Project Services Manager| Rio Tinto Gilbert, Az, United States
We use EV principles, and tailored EVM to project specific needs. Certainly it adds lot of value especially in major projects. i am in mining
...
1 reply by Vincent Guerard
Oct 05, 2017 9:51 PM
Vincent Guerard
...
Thanks for you input
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
EVM calculation about to predict the project future from actuals is what more useful in my case.
...
1 reply by Vincent Guerard
Oct 05, 2017 9:52 PM
Vincent Guerard
...
Thanks Sergio
So you use just actual
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Vincent -

Forecasting on projects following agile delivery practices such as letting past iteration/sprint velocity determine when the team will complete a release or product backlog is a modified approach to EV which is practiced on many projects.

I've rarely seen pure EVA & variance analysis (to use the PMBOK v6 terms :-) ) used in the companies I've supported as they lack the work package level cost reporting and/or work decomposition discipline needed to practice it accurately.

Kiron
...
1 reply by Vincent Guerard
Oct 05, 2017 9:53 PM
Vincent Guerard
...
Thanks , interesting
avatar
Mike Dewing Senior Project Manager / Program Manager| MLD Holdings Ltd. Surrey, British Columbia, Canada
Similar to Vincent - not used as outline in PMBok, we typically use other models that the finance gods live eat and die by which aligns more closely to their business needs. the concepts are there just the process is different.
...
1 reply by Vincent Guerard
Oct 05, 2017 9:54 PM
Vincent Guerard
...
Thanks
avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
Oct 05, 2017 4:06 PM
Replying to Krishna Pakki
...
We use EV principles, and tailored EVM to project specific needs. Certainly it adds lot of value especially in major projects. i am in mining
Thanks for you input
avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
Oct 05, 2017 4:07 PM
Replying to Sergio Luis Conte
...
EVM calculation about to predict the project future from actuals is what more useful in my case.
Thanks Sergio
So you use just actual
avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
Oct 05, 2017 5:46 PM
Replying to Kiron Bondale
...
Vincent -

Forecasting on projects following agile delivery practices such as letting past iteration/sprint velocity determine when the team will complete a release or product backlog is a modified approach to EV which is practiced on many projects.

I've rarely seen pure EVA & variance analysis (to use the PMBOK v6 terms :-) ) used in the companies I've supported as they lack the work package level cost reporting and/or work decomposition discipline needed to practice it accurately.

Kiron
Thanks , interesting
avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
Oct 05, 2017 6:10 PM
Replying to Mike Dewing
...
Similar to Vincent - not used as outline in PMBok, we typically use other models that the finance gods live eat and die by which aligns more closely to their business needs. the concepts are there just the process is different.
Thanks
avatar
Br. Ts. PUI CHEE KHIAN PMP®, PMI-RMP®, PMI-SP, CCPM (CIDB), MBA, MPM® CPE, FAAPM, FCILG, MPMI, | CPE, FAAPM, FCILG, MPMI, MMSSA, MMIM, AMIVMM, CM(ACPM) Kuching, Sarawak, Malaysia
Our Project Team (Construction Project) use Primavera P6 extensively as contractual specified tool in project management.
...
1 reply by Vincent Guerard
Nov 07, 2017 5:20 PM
Vincent Guerard
...
I not experience on Primavera P6 full usage. When well populated the calculation of EVM work good?
avatar
Stéphane Parent Self Employed / Semi-retired| Leader Maker Prince Edward Island, Canada
I have been doing IT project management for over twenty years, Vincent. We definitely use the EVM indices (CPI and SVI) to see if we are off track. EAC is not used very much.
...
1 reply by Vincent Guerard
Nov 07, 2017 5:21 PM
Vincent Guerard
...
That is also my experience in most project the basic is use.
< 1 2 3 4 >

Please login or join to reply

Content ID:
ADVERTISEMENTS

Disbelief in magic can force a poor soul into believing in government and business.

- Tom Robbins

ADVERTISEMENT

Sponsors