Who are recognised under PMBOK to put up a Change Request?

linkedin twitter facebook   Governance  
avatar
Br. Ts. PUI CHEE KHIAN PMP®, PMI-RMP®, PMI-SP, CCPM (CIDB), MBA, MPM® CPE, FAAPM, FCILG, MPMI, | CPE, FAAPM, FCILG, MPMI, MMSSA, MMIM, AMIVMM, CM(ACPM) Kuching, Sarawak, Malaysia
A. Project Manager
B. Project Team
C. Stakeholder
D. Project Sponsor/Initiator
E. All the above
Sort By:
avatar
Anonymous
Chee Khian
Clarify what you mean by "put". Do you mean request or approve? If request, it is all of the above and if approve depends on the type of change (within objective PM, changes to objective it would be sponsor)

But i have not checked this point in the new guide yet but should not be any different.
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Agreed with Mounir -

anyone can theoretically submit a change request, but depending on the specific governance established for the project the Sponsor or some other senior leader (or committee) would approve it.

Kiron
avatar
Stéphane Parent Self Employed / Semi-retired| Leader Maker Prince Edward Island, Canada
Anyone should be able to bring change requests to the change control board (CCB). The CCB will then approve using time and resources to assess the request. Once the assessment is completed, it is presented to the CCB for consideration and decision.
avatar
Br. Ts. PUI CHEE KHIAN PMP®, PMI-RMP®, PMI-SP, CCPM (CIDB), MBA, MPM® CPE, FAAPM, FCILG, MPMI, | CPE, FAAPM, FCILG, MPMI, MMSSA, MMIM, AMIVMM, CM(ACPM) Kuching, Sarawak, Malaysia
Dear Mounir Ajam, Kiron Bondale & Stephen Parent,

Thank you for the reply. Appreciate a lot.