It is about midway through your current project and some of your stakeholders have informed you that their needs have changed on the project. As a result, you will need adjust your strategy and plans for engaging stakeholders for the remainder of the project. What process are you in?
A. Control Stakeholder Engagement
B. Plan Stakeholder Management
C. Manage Stakeholder Engagement
D. Identify Stakeholders
Stakeholders have informed you - interacted with you. C is mainly about keep stakeholders involved and informed. That would be my explanation why C is correct. Saving Changes...
PINTU DEBNATHPM I| Tata Consultancy ServicesBangalore, Ka, India
engaging stakeholders - key for the answer. You are already in mid of the project, hence option B and D not possible. Saving Changes...
Manage Stakeholder Engagement can lead to Control Stakeholder Engagement via updates to the Issue Log. The second sentence in the body of the question is clearly related to Control Stakeholder Engagement, but that is the next process you will proceed to - right now, you are in Manage Stakeholder Engagement as you are actively communicating and working with stakeholders.
you are in the midway of project and "adjust your strategy and plans for engaging stakeholders" means that you managing their engagement. D and B were completed in early stages. Saving Changes...
Senior Projects Manager | Field & Marten AssociatesNew Westminster, British Columbia, Canada
If you need to adjust your strategy and plans for engaging stakeholders it mean you are in the process of managing them but the question is not very clear as well. Saving Changes...
MICHAIL KOSTOUROSSENIOR PROJECT MANAGER, MSc,PMP,RMP,MCP,CIVIL ENGINEER| TECHNIKI 2000 S.A.Chalkida, Greece
Because you're in the midway it means that you are at the execution stage and you will adjust your strategy and plans in the future: Control stakeholders. So the right answer is C. Saving Changes...
Glenn SmithService Manager- Denver, CO Branch| Evoqua Water TechnologiesAurora, Co, United States
You are past the Initiating stage (answer D) and past the Planning stage (answer B).If you are looking at "adjusting your strategy and plans for stakeholder engagement, you are managing this process (Correct answer C). After that, you can Control the stakeholder engagement correctly (answer A). Saving Changes...
Mahabubur RahmanProject Manager Structures-Bridges| Department of Infrastructure, Government of Nothwest TerritoriesYellowknife, Northwest Territories, Canada
This question is a tricky one! "Communication" and in the "midway of your project" meaning you are in the executing process group. And Manage SHE process falls in this PG. So the answer is C. Saving Changes...