ATHANASIOS GKOLAS PMP - PMI-RMP-BIM Manager | OMITEM Consulting Engineers S.A Athens, Greece
It is about midway through your current project and some of your stakeholders have informed you that their needs have changed on the project. As a result, you will need adjust your strategy and plans for engaging stakeholders for the remainder of the project. What process are you in?

A. Control Stakeholder Engagement
B. Plan Stakeholder Management
C. Manage Stakeholder Engagement
D. Identify Stakeholders

Why is C the right answer
Sort By:
< 1 2 >
avatar
Peter Ambrosy Weinheim, Germany
Stakeholders have informed you - interacted with you. C is mainly about keep stakeholders involved and informed. That would be my explanation why C is correct.
avatar
PINTU DEBNATH PM I| Tata Consultancy Services Bangalore, Ka, India
engaging stakeholders - key for the answer. You are already in mid of the project, hence option B and D not possible.
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Athanasios -

Manage Stakeholder Engagement can lead to Control Stakeholder Engagement via updates to the Issue Log. The second sentence in the body of the question is clearly related to Control Stakeholder Engagement, but that is the next process you will proceed to - right now, you are in Manage Stakeholder Engagement as you are actively communicating and working with stakeholders.

Kiron
avatar
Abolfazl Yousefi Darestani Manager, Quality and Continuous Improvement| Hörmann-TNR Industrial Doors Newmarket, Ontario, Canada
you are in the midway of project and "adjust your strategy and plans for engaging stakeholders" means that you managing their engagement. D and B were completed in early stages.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
If you need to adjust your strategy and plans for engaging stakeholders it mean you are in the process of managing them but the question is not very clear as well.
avatar
MICHAIL KOSTOUROS SENIOR PROJECT MANAGER, MSc,PMP,RMP,MCP,CIVIL ENGINEER| TECHNIKI 2000 S.A. Chalkida, Greece
Because you're in the midway it means that you are at the execution stage and you will adjust your strategy and plans in the future: Control stakeholders. So the right answer is C.
avatar
Glenn Smith Service Manager- Denver, CO Branch| Evoqua Water Technologies Aurora, Co, United States
You are past the Initiating stage (answer D) and past the Planning stage (answer B).If you are looking at "adjusting your strategy and plans for stakeholder engagement, you are managing this process (Correct answer C). After that, you can Control the stakeholder engagement correctly (answer A).
avatar
Mahabubur Rahman Project Manager Structures-Bridges| Department of Infrastructure, Government of Nothwest Territories Yellowknife, Northwest Territories, Canada
This question is a tricky one! "Communication" and in the "midway of your project" meaning you are in the executing process group. And Manage SHE process falls in this PG. So the answer is C.
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
There's nothing like consensus.
avatar
ATHANASIOS GKOLAS PMP - PMI-RMP-BIM Manager | OMITEM Consulting Engineers S.A Athens, Greece
I would like to thank you all for your contribution. Your answers are very helpful and cover every aspect of this question.
< 1 2 >

Please login or join to reply

Content ID:
ADVERTISEMENTS

"You do not really understand something unless you can explain it to your grandmother."

- Albert Einstein

ADVERTISEMENT

Sponsors