Delayed tasks

linkedin twitter facebook   PMO  
avatar
Daniel Segal Israel
Hi, I would like to know what is the best way to display the delayed tasks on the Gantt chart? I want to have an indication that the project is delayed, but still see a new due date for the tasks.
Thanks, Daniel.
Sort By:
avatar
Stéphane Parent Self Employed / Semi-retired| Leader Maker Prince Edward Island, Canada
If you are using Microsoft Project, you would change the Gantt display to show both the current and baseline schedule.
avatar
Ahmad Yahya CEO| ADAM - Agile Digital Assistant for Managers Putrajaya, Malaysia
Publish your latest baseline and your current schedule.
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Daniel -

Depending on the version of MSP you are using, you can also filter most task views by delayed tasks to only show those...

Kiron

Please login or join to reply

Content ID:
ADVERTISEMENTS

"When one door closes another door opens; but we often look so long and so regretfully upon the closed door that we do not see the ones which open for us."

- Alexander Graham Bell

ADVERTISEMENT

Sponsors