I got a question for Micro master " What is the best project methodology?"
and there was some 3 choices ( TPM(traditional project management, APM Agile Project management , Critical chain Project management ).
I was very surprise about question, because as I knew the project management methodology is a system of practices, Technics,procedures and rules used by organization or by project manager.
For Example when both the scope and deliverable targets are known from the beginning I should choose the (TPM traditional project methodology).
However if the deliverable target are known and the COMPLETELY known it is prefer to use (APM as we will develop the products elaborately until we satisfied a bout the product). (for example developing WEB side ).
There is another one which called hybrid one.
In Summary there is no best or worst methodology, it is depend on project which I have it.
It is very subjective, and there is no absolutely correct answer. Saving Changes...
Drake SettsuProject Manager / BloggerHi, United States
Good comments fom the group.
It comes down to judgemnt and gut feeling what will work best to run the project. The successful Project Manager will need to have a toolbox of Project Management Methods, Approaches & Techniques.
In the real world, there is no such "best methodology" rather I would use"Best Suitable methodology for the moment/project"
If the scope is clearly defined and not changeable in the future go for TPM
Agile focuses less on specific requirements or guidelines, and allow for greater flexibility, or agility, during the development process.
In exams, answer the question based on the context. Saving Changes...