WBS dictionary

linkedin twitter facebook   Estimating   Work Breakdown Structures (WBS)  
avatar
Ahmed Karar Project Engineer| Ministry of Water Resources, Irrigation and Electricity Khatoum, Khatoum/ Jabl Awlia, Sudan
Information in the WBS dictionary may include but is not limited to:
Code of account identifier,
Description of work,
Assumptions and constraints,
Responsible organization,
Schedule milestones,
Associated schedule activities,
Resources required,
Cost estimates,
Quality requirements,
Acceptance criteria,
Technical references, and
Agreement information.
_____________________

I quoted the above list from PMBOK6, how I find the Associated schedule activities,
and other information before their process started note that WBS dictionary is part of scope baseline which should be change only as per formal change request. and how it comes to have incomplete baseline at first place
Sort By:
< 1 2 >
avatar
Ali Hossam Sr.Planning Engineer| CCC Qatar
This article may help
https://bibloteka.com/how-to-create-a-prof...wbs-dictionary/
< 1 2 >

Please login or join to reply

Content ID:
ADVERTISEMENTS

"Smoking is one of the leading causes of statistics."

- Fletcher Knebel

ADVERTISEMENT

Sponsors