Project Cost Constraint

linkedin twitter facebook   Estimating   Work Breakdown Structures (WBS)  
avatar
azrul shah ismail Managing Director| iSeal Solution Sdn Bhd Malaysia
My management instruct me to take up a halfway project that having a cost constraint (38 million to complete the project). What's your next action? How should you response to this situation?
Sort By:
< 1 2 >
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Making the estimations. To make the estimations you need to know the product/service/result to create and then perform the math based on resources and time. Do not forget Barry Bohem´s Cone of Uncertainty that was created for software products but has been taken for lot of others disciplines (including the PMBOK GUide in other versiones).
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Azrul -

As Sergio indicates, when handed a cost constraint, it is in everyone's best interests to determine whether minimally acceptable scope can be delivered in a reasonable time frame within that cost constraint.

Based on what has been spent to date and what has been delivered, you'd want to calculate an EAC (taking into account the cone of uncertainty) and see if it will fit or not.

If not, better to have the hard discussion sooner rather than later with your management team!

Kiron
avatar
Anish Abraham Privacy Program Manager| University of Washington Auburn, Wa, United States
I agree with Kiron on this.

I think the key to managing the cost constraint and ultimately having a successful project is transparency. This means team members and all stakeholders should be kept informed, priorities should be set, and everybody should fully understand the project objectives.
avatar
Jose Luis Gonzalez Rugel Presidente Grupo Gonzalez - Program Manager - Docente- Consultor - ATP Trainner| Dipromacom Guayaquil, Guayas, Ecuador
I agreed with Sergio. The next step is to work makinn the estimation. I suggestion work the estimation with all stakeholder for to have the more exactly values.
If the estimation is less than the current budget, it is necessary to speak with the sponsor
avatar
Drew Craig Sr. Agile & Product Coach| Vanguard Philadelphia, Pa, United States
Agree with above. Where are you now compared to where you need to be in conjunction with the expected completion date.
...
1 reply by azrul shah ismail
Jan 07, 2018 11:49 AM
azrul shah ismail
...
Thanks all for the feedback. Answering Andrew question, the project completion as of to date only reached 43% and 18% delayed. Looking at the project ROI after simulated the deliverable tie to the project costing, scope and timeline , it takes me another 10 months to normalize the project cost subject to other sponsor availability from another government agencies to take over funding the project immediately. 10 months duration its to long for me and shall jeopardize my company profit and heavily contribute a big loss to the company. I've brought this up to management attention to withdraw the project else it shall impact the company profit and demotivate the project resources.

I can see the the main sponsor hard to make any decision in the steering committee meeting due the cost constraint its to huge to absorb. I've suggested them to stop the project and start to conduct a special exercise such as re-baseline the scope, schedule and urgently perform the financial evaluation with the project team and the sponsor to decide. But today it seems the proposal not being agreed by the key committee but asking me to continue the project until its completion. This is a nightmare bro..
avatar
Riyadh Salih Saskatchewan, Canada
Thanks Sergio,he mentioned a powerful model calculations of the cone to help you out with other estimation techniques, once you have more clear numbers on the funnel of attrition and all risk reassessed you can move on with your determined budget.
avatar
Najam Mumtaz Retired Lahore, Punjab, Pakistan
I am sure cost you mentioned is not the only constraint you have. There must be a schedule and a scope that has to be completed (of course). The first thing I would do is, check the health of baselines to know where the project stands at that point. And that is what EVM or project/ performance measurements will tell you. Than taking at least the key stakeholders on board before I get on with the project.
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Even before estimates, find out if scope and/or schedule can be flexible (obviously not quality). The reason? Depending on what they say, it might effect your estimated because of contingency and reserve factors.
avatar
Thomas Walenta Global Project Economy Expert Hackenheim, Germany
The cost constraint might just by a symptom of other problems.
I recommend to do a end2end project assessment, starting with interviewing the key stakeholders 1:1 to find out the key issues.
avatar
Mansoor Mustafa Senior PM| Government Department Rawalpindi Punjab, Pakistan
Agree with Kiron and Anish
Managing the cost constraint project and transparency in project is ultimate objective, all stakeholder must be knowing what all can be achievable from the given cost, right from start of project, so that priorities should be set and everybody on board