I applied for the PMP examination last week and received my eligibility to pay for the exam yesterday. I payed for the exam and received an email stating "You may now contact Prometric to schedule your Project Management Professional (PMP) credential examination."

How long before I will know if I will be selected for an audit, or does this mean that I am not being audited and I may take the exam when I desire?

Thank you for your time and assistance. I greatly appreciate it.

Mike
Sort By:
avatar
Josh Nankivel Engineering Project Manager| Apple Sioux Falls, Sd, United States
From what I understand, only a percentage of people sitting for the PMP exam are audited, usually after they've taken it. If they accepted your application you should be good to go to take the exam.
avatar
George Jucan Managing Partner| Organizational Perfomance Enablers Network Woodbridge, Ontario, Canada
Josh is right, only a percentage is audited so you can go ahead and book your exam (if you got your notification you were not selected for audit). However, PMI can audit your application even years down the road, usually if they receive a complaint or such, so keep any supporting documentation for at least couple of years.
avatar
Bipin Lekshmanan PMP Project Manager| Wipro Technologies Edison, Nj, United States
I only know about two of my colleagues getting audited by PMI. That was almost immediately after they got certified as PMP.
avatar
Anonymous
In PMP Application can i specify supervisor names who have left the organization but can be contacted and are ready to verifiy my work ?
I am asking this because i have switched my organization and the people i had worked under in the previous organization have now left and there are new guys in those posts.
avatar
Anonymous
I am ready to fill my PMP application. What has to be written in the experience verification form part 3 ? It talks about the deliverables. I have decided on the following: Kindly guide me

Initiation

Developed Project Charter, Developed Perliminary Scope Statement

Planning
Developed Project Management Plan, Planned and Defined the Scope,Created the Work breakdown structure, Defined activities, sequenced activities, did the

resource estimation of activities,duration estimation of activities, developed the schedule, did cost estimation and budgeting, did quality and human

resource planning, did communication planning, risk management planning, risk identification,risk analysis, response planning, plan purchases and

acquisitions, plan contracting


Execution
Directed and manage execution,perform quality assurance, acquired and developed project team,distributed the information, requested seller responses and

selected sellers


Monitoring and Control
Monitored and controlled work, did change control, did scope verification and control, schedule control, cost control, quality control, managed the project

team, performance reporting, managed stakeholders, risk monitoring and control, contract administration,

Closure

Closed project, contract closure


avatar
George Jucan Managing Partner| Organizational Perfomance Enablers Network Woodbridge, Ontario, Canada
It's been some years now since I filled mine, but as far as I remember that section was more in terms of:
- created Project Communication Plan
- contributed with effort and duration estimates to Project Schedule
- provided roles, responsibilities and skills descriptions for theProject Resources Plan

The deliverable is usually a document or something tangible.

Hope it helps.