Project Management

Please login or join to subscribe to this thread

What was the best risk mitigation you have applied in your previous projects?

linkedin twitter facebook   Risk Management  
avatar
Samer Alhmdan Senior Project Manager, PMP, PMI-RMP, LEED AP, EDGE Expert| dar Dubai, United Arab Emirates
What was the best risk mitigation you have applied in your previous projects?
Sort By:
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Well the easiest is probably transferring it, but the enjoyable one is avoiding the risk the best way possible.
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Samer -

If you are strictly looking at mitigation (i.e. reducing probability and/or impact), then building buffer into a project timeline between an internal milestone target date and the committed customer date has always worked well for me.

However, I'd second Sante's feedback as my favorite risk response is avoidance, especially at the onset of a project, where you have the opportunity to jettison particularly risky scope elements in order to reduce the project's overall risk profile.

Kiron
avatar
Najam Mumtaz Retired Lahore, Punjab, Pakistan
Getting the right project team to do the work. By "right" I mean people with skills suitable for project.
avatar
Samer Alhmdan Senior Project Manager, PMP, PMI-RMP, LEED AP, EDGE Expert| dar Dubai, United Arab Emirates
Thank you ALL for sharing your valued knowledge.
avatar
Jim Branden Senior Project Manager| Retired from UNC Charlotte - IT Services - PPMO Charlotte, Nc, United States
Samer, as a PM-instructor, I shock many people with this comment, "Mitigation is the third worst way to deal with negative risks!" I'll condense my one-hour lecture into the key conclusions: 1-Avoid all negative risks, if you can. 2-If you cannot avoid the risk, transfer it to someone better able to deal with it. 3-If you cannot pay someone to take the risk (transfer), and then break it down into manageable parts so that the sum of the probabilities and impacts is less than the unmitigated risk. 4-If you cannot mitigate the risk, accept it with a Plan B, Plan C, Plan D, etc. (Remember all plans including B – Z contain risks unique to each alternative plan!).
To answer your question, my best mitigation technique was designating “lead”, “support” and “as needed” teams for each of the key portions of a large project. Knowing that if the “A-team” became overworked, the “B- and C-teams” were standing by gave the Sponsor and team peace of mind. It also motivated the “A-team” to work to avoid (notice that word) needing the B-team! Jim
avatar
Samer Alhmdan Senior Project Manager, PMP, PMI-RMP, LEED AP, EDGE Expert| dar Dubai, United Arab Emirates
Thank you Jim for your valued answer.
avatar
Samer Alhmdan Senior Project Manager, PMP, PMI-RMP, LEED AP, EDGE Expert| dar Dubai, United Arab Emirates
Thank you ALL for sharing your valued knowledge.

Please login or join to reply

Content ID:
ADVERTISEMENTS

"Experience is a comb which nature gives to men when they are bald."

- Chinese Proverb

ADVERTISEMENT

Sponsors